Table of Contents
- Eaton® 93E UPS 40–60 kVA (208/220V) Generation 3 Installation and Operation Manual
- Table of Contents
- List of Figures
- List of Tables
- Chapter 1 Introduction
- 1.1 UPS Standard Features
- 1.2 Options and Accessories
- 1.2.1 External Battery Cabinet Capability
- 1.2.2 External Battery Cabinet
- 1.2.3 Integrated Accessory Cabinet-Distribution
- 1.2.4 Sidecar Integrated Accessory Cabinet-Bypass
- 1.2.5 Integrated Transformer Cabinet
- 1.2.6 Integrated Accessory Cabinet-Tie
- 1.2.7 Integrated Accessory Cabinet-Tie and Bypass
- 1.2.8 Reduced Battery String Model
- 1.2.9 kVA Upgrades
- 1.2.10 Parallel System
- 1.2.11 Monitoring and Communication
- 1.2.12 Dual Feed
- 1.3 Basic System Configurations
- 1.4 Using This Manual
- 1.5 Conventions Used in This Manual
- 1.6 Symbols, Controls, and Indicators
- 1.7 For More Information
- 1.8 Getting Help
- Chapter 2 Safety Warnings
- Section 1 Installation
- Chapter 3 UPS Installation Plan and Unpacking
- Chapter 4 UPS System Installation
- 4.1 Preliminary Installation Information
- 4.2 Unloading the UPS Cabinet from the Pallet
- 4.3 Installing Power Terminal Cover Base
- 4.4 External Battery Cabinet Installation
- 4.5 Integrated Transformer Cabinet Installation
- 4.6 Sidecar Integrated Accessory Cabinet-Bypass
- 4.7 Integrated Accessory Cabinet-Tie
- 4.8 Integrated Accessory Cabinet-Tie and Bypass
- 4.9 Integrated Accessory Cabinet-Distribution
- 4.10 External Power Wiring Installation
- 4.11 Installing Interface Connections
- 4.12 Installing a REPO Switch
- 4.13 Connecting Internal Battery Strings
- 4.14 Initial Startup
- 4.15 Completing the Installation Checklist
- Section 2 Operation
- Chapter 5 Understanding UPS Operation
- Chapter 6 UPS Operating Instructions
- 6.1 UPS Controls and Indicators
- 6.2 Using the Control Panel
- 6.3 Single UPS Operation
- 6.3.1 Starting the UPS in High-Efficiency Normal Mode (Default Mode)
- 6.3.2 Starting the UPS in Bypass Mode
- 6.3.3 Transfer from Normal to Bypass Mode
- 6.3.4 Transfer from Bypass to Normal Mode
- 6.3.5 Transfer from HE Normal Mode to Standard Normal Mode
- 6.3.6 Transfer from Standard Normal Mode to HE Normal mode
- 6.3.7 UPS and Critical Load Shutdown
- 6.3.8 Charger Control
- 6.3.9 Battery Test
- 6.3.10 Using the UPS LOAD OFF Command
- 6.3.11 Using the Remote Emergency Power-off Switch
- 6.4 Multiple UPS Parallel Operation
- 6.4.1 Starting the Parallel UPS in High-Efficiency Normal Mode (Default Mode)
- 6.4.2 Starting the Parallel UPS in Bypass Mode
- 6.4.3 Transfer from Normal to Bypass Mode
- 6.4.4 Transfer from Bypass to Normal Mode
- 6.4.5 Transfer from HE Normal Mode to Standard Normal Mode
- 6.4.6 Transfer from Standard Normal Mode to HE Normal mode
- 6.4.7 Single UPS Shutdown
- 6.4.8 Single UPS Restart
- 6.4.9 UPS and Critical Load Shutdown
- 6.4.10 Charger Control
- 6.4.11 Battery Test
- 6.4.12 Using the UPS LOAD OFF Command
- 6.4.13 Using the Remote Emergency Power-off Switch
- Chapter 7 Communication
- Chapter 8 UPS Maintenance
- Chapter 9 Product Specifications
- Warranty
Eaton 93E User Manual
Displayed below is the user manual for 93E by Eaton which is a product in the Uninterruptible Power Supplies (UPSs) category. This manual has pages.
Related Manuals
Eaton® 93E UPS
40–60 kVA (208/220V)
Generation 3
Installation and Operation Manual
Eaton® 93E UPS
40–60 kVA (208/220V)
Generation 3
Installation and Operation Manual
IMPORTANT SAFETY INSTRUCTIONS SAVE THESE INSTRUCTIONS
This manual contains important instructions that you should follow during installation and
maintenance of the UPS and batteries. Please read all instructions before operating the equipment
and save this manual for future reference.
CONSIGNES DE SÉCURITÉ IMPORTANTES CONSERVER CES INSTRUCTIONS
Ce manuel comporte des instructions importantes que vous êtes invité à suivre lors de toute
procédure d'installation et de maintenance des batteries et de l'onduleur. Veuillez consulter
entièrement ces instructions avant de faire fonctionner l'équipement et conserver ce manuel afin
de pouvoir vous y reporter ultérieurement.
Eaton, Powerware, and Mini-Slot are registered trademarks and ConnectUPS is a trademark of Eaton or its
subsidiaries and affiliates. Modbus is a registered trademark of Schneider Electric. National Electrical Code and
NEC are registered trademarks of National Fire Protection Association, Inc. All other trademarks are property
of their respective companies.
©Copyright 2013–2016 Eaton, Raleigh, NC, USA. All rights reserved. No part of this document may be
reproduced in any way without the express written approval of Eaton.
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 i
Table of Contents
1 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1
1.1 UPS Standard Features . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2
1.1.1 Installation Features. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2
1.1.2 Control Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2
1.1.3 Customer Interface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2
1.1.4 High-Efficiency Normal Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2
1.1.5 Battery System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2
1.1.6 Advanced Battery Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2
1.2 Options and Accessories. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.2.1 External Battery Cabinet Capability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.2.2 External Battery Cabinet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.2.3 Integrated Accessory Cabinet-Distribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.2.4 Sidecar Integrated Accessory Cabinet-Bypass . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.2.5 Integrated Transformer Cabinet. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.2.6 Integrated Accessory Cabinet-Tie . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.2.7 Integrated Accessory Cabinet-Tie and Bypass . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.2.8 Reduced Battery String Model . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4
1.2.9 kVA Upgrades . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4
1.2.10 Parallel System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4
1.2.11 Monitoring and Communication . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4
1.2.12 Dual Feed. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4
1.3 Basic System Configurations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4
1.4 Using This Manual. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5
1.5 Conventions Used in This Manual. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5
1.6 Symbols, Controls, and Indicators. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5
1.7 For More Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-6
1.8 Getting Help . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-6
2 SAFETY WARNINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1
SECTION 1 — INSTALLATION
3 UPS INSTALLATION PLAN AND UNPACKING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1
3.1 Creating an Installation Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1
3.2 Preparing the Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1
3.2.1 Environmental and Installation Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1
3.2.2 UPS System Power Wiring Preparation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-7
3.2.3 UPS System Interface Wiring Preparation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-12
3.3 Battery Type . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13
3.4 Inspecting and Unpacking the UPS Cabinets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13
4 UPS SYSTEM INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1
4.1 Preliminary Installation Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1
4.2 Unloading the UPS Cabinet from the Pallet. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1
4.3 Installing Power Terminal Cover Base. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-6
4.4 External Battery Cabinet Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-8
4.5 Integrated Transformer Cabinet Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-8
Table of Contents
ii Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
4.6 Sidecar Integrated Accessory Cabinet-Bypass . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-8
4.7 Integrated Accessory Cabinet-Tie . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-8
4.8 Integrated Accessory Cabinet-Tie and Bypass . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-8
4.9 Integrated Accessory Cabinet-Distribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-8
4.10 External Power Wiring Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-9
4.11 Installing Interface Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-13
4.11.1 Installing Building Alarm Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-13
4.11.2 Generator Interface Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-18
4.11.3 Installing Parallel Pull Chain and CAN Control Wiring and Connections . . . . . . . . . . . . . . . . . . . . . . . . 4-19
4.11.4 Installing Mini-Slot Interface Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-20
4.12 Installing a REPO Switch. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-22
4.13 Connecting Internal Battery Strings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-25
4.14 Initial Startup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-28
4.15 Completing the Installation Checklist . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-28
SECTION 2 — OPERATION
5 UNDERSTANDING UPS OPERATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1
5.1 UPS System Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1
5.2 Single UPS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1
5.2.1 Modes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-2
5.2.2 High-Efficiency Normal Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-2
5.2.3 Standard Normal Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-2
5.2.4 Bypass Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-4
5.2.5 Battery Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-5
5.3 Single UPS Unit System Oneline Configurations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-6
6 UPS OPERATING INSTRUCTIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1
6.1 UPS Controls and Indicators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1
6.1.1 Control Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-2
6.1.2 Circuit Breakers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-2
6.2 Using the Control Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-3
6.2.1 Status Indicators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-3
6.2.2 System Events . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-4
6.2.3 Using the LCD and Pushbuttons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-5
6.2.4 Using the Menu. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-6
6.2.5 Mimic Screen . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-6
6.2.6 Display Menu Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-7
6.2.7 System Controls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-9
6.3 Single UPS Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-11
6.3.1 Starting the UPS in High-Efficiency Normal Mode (Default Mode) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-11
6.3.2 Starting the UPS in Bypass Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-12
6.3.3 Transfer from Normal to Bypass Mode. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-13
6.3.4 Transfer from Bypass to Normal Mode. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-13
6.3.5 Transfer from HE Normal Mode to Standard Normal Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-13
6.3.6 Transfer from Standard Normal Mode to HE Normal mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-14
6.3.7 UPS and Critical Load Shutdown. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-14
6.3.8 Charger Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-14
6.3.9 Battery Test. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-15
Table of Contents
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 iii
6.3.10 Using the UPS LOAD OFF Command . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-15
6.3.11 Using the Remote Emergency Power-off Switch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-16
6.4 Multiple UPS Parallel Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-17
6.4.1 Starting the Parallel UPS in High-Efficiency Normal Mode (Default Mode) . . . . . . . . . . . . . . . . . . . . . 6-17
6.4.2 Starting the Parallel UPS in Bypass Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-18
6.4.3 Transfer from Normal to Bypass Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-19
6.4.4 Transfer from Bypass to Normal Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-19
6.4.5 Transfer from HE Normal Mode to Standard Normal Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-19
6.4.6 Transfer from Standard Normal Mode to HE Normal mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-20
6.4.7 Single UPS Shutdown . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-20
6.4.8 Single UPS Restart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-20
6.4.9 UPS and Critical Load Shutdown . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-21
6.4.10 Charger Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-22
6.4.11 Battery Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-22
6.4.12 Using the UPS LOAD OFF Command . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-22
6.4.13 Using the Remote Emergency Power-off Switch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-23
7 COMMUNICATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-1
7.1 Mini-Slot Cards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-1
7.2 Building Alarm Monitoring. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-2
7.3 Predict Pulse Remote Monitoring and Management Service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-2
7.3.1 PredictPulse Service Features . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-3
7.3.2 Installing PredictPulse . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-3
8 UPS MAINTENANCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-1
8.1 Important Safety Instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-1
8.2 Performing Preventive Maintenance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-2
8.2.1 DAILY Maintenance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-2
8.2.2 MONTHLY Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-2
8.2.3 ANNUAL Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-3
8.2.4 BATTERY Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-3
8.3 Installing Batteries. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-3
8.4 Recycling the Used Battery or UPS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-4
8.5 Maintenance Training . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-4
9 PRODUCT SPECIFICATIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-1
9.1 Model Numbers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-1
9.2 Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-1
9.2.1 UPS Input. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-1
9.2.2 UPS Output . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-2
9.2.3 UPS Environmental . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-2
9.2.4 UPS Internal Battery Runtimes (in Minutes) at Full load . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-2
9.2.5 UPS Internal Battery Plus External Battery Cabinet Runtimes (in Minutes) at Full load . . . . . . . . . . . 9-3
WARRANTY. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . W-1
Table of Contents
iv Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
This page intentionally left blank.
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 v
List of Figures
Figure 1-1. Eaton 93E UPS (40–60 kVA) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1
Figure 3-1. UPS Cabinet Dimensions (Front and Right Side Views) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-4
Figure 3-2. UPS Cabinet Dimensions (Top and Bottom Views). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-5
Figure 3-3. UPS Cabinet Center of Gravity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-6
Figure 3-4. Remote EPO Switch Dimensions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-7
Figure 3-5. UPS Cabinet as Shipped on Pallet (wood container removed) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-15
Figure 4-1. Removing the Front Shipping Bracket. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-2
Figure 4-2. Attaching the Ramp to the Pallet. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-3
Figure 4-3. Removing the Rear Shipping Bracket . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-4
Figure 4-4. Rolling the Cabinet Down the Ramp . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-5
Figure 4-5. UPS Power Terminal Cover Parts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-6
Figure 4-6. UPS Power Terminal Cover Base Installation and Conduit Landing Wire Entry Locations . . . . . . . . . . . . . . 4-7
Figure 4-7. Power Terminal Locations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-10
Figure 4-8. Power Terminal Detail . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-11
Figure 4-9. Power Terminal Cover Top Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-12
Figure 4-10. Interface Terminal Locations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-13
Figure 4-11. Interface Terminal Detail (Terminal Cover Removed) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-14
Figure 4-12. Building Alarm Terminal Block Connector Assignments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-14
Figure 4-13. Interface Terminal Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-16
Figure 4-14. Interface Conduit Landing and Wiring Channel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-17
Figure 4-15. Interface Wiring Access . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-17
Figure 4-16. Pull Chain Terminal Block Connector Assignments. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-19
Figure 4-18. REPO Switch. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-22
Figure 4-19. REPO Terminal Block Connector Assignments. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-23
Figure 4-20. Normally-Open REPO Switch Wiring. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-24
Figure 4-21. Normally-Closed REPO Switch Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-25
Figure 4-22. Battery Location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-26
Figure 4-23. Battery Section . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-27
Figure 4-24. Battery String Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-28
Figure 5-1. Main Elements of the UPS System. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1
Figure 5-2. Path of Current Through the UPS in standard Normal Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-3
Figure 5-3. Path of Current Through the UPS in Bypass Mode. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-4
Figure 5-4. Path of Current Through the UPS in Battery Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-5
Figure 5-5. UPS System Oneline – 93E-40 Internal Battery (No External Battery Capability) . . . . . . . . . . . . . . . . . . . . . 5-7
Figure 5-6. UPS System Oneline – Internal Battery and External Battery Capable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-8
Figure 5-7. UPS System Oneline – Internal and External Batteries . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-9
Figure 6-1. UPS Controls and Indicators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1
Figure 6-2. UPS Breakers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-2
Figure 6-3. UPS Control Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-3
Figure 6-8. REPO Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-16
Figure 7-1. Optional Mini-Slot Cards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-1
Figure 8-1. Air Filter Location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-3
List of Figures
vi Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
This page intentionally left blank.
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 vii
List of Tables
Table 3-1. Combined Altitude and Thermal Derating Factors. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-2
Table 3-2. Air Conditioning or Ventilation Requirements During Full Load Operation . . . . . . . . . . . . . . . . . . . . . . . . . . 3-2
Table 3-3. UPS Cabinet Weights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-3
Table 3-4. UPS Cabinet Clearances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-3
Table 3-5. Input/Output Ratings and External Wiring Requirements for the Eaton 93E-40,
93E–60/40, and 93E–60/60 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-9
Table 3-6. UPS External Power Cable Terminations for the Eaton 93E-40, 93E–60/40, and 93E–60/60 . . . . . . . . . . . . 3-10
Table 3-7. Power Cable Conduit Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-11
Table 3-8. Recommended Input Circuit Breaker Ratings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-11
Table 3-9. Recommended Bypass and Output Circuit Breaker Ratings. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-12
Table 3-10. Battery Type . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13
Table 4-1. Building Alarm Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-14
Table 4-2. Pull Chain Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-19
Table 4-3. REPO Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-23
Table 4-4. Normally-Open REPO Wire Terminations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-24
Table 4-5. Normally-Closed REPO Wire Terminations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-24
Table 6-1. Status Indicators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-3
Table 6-2. Display Function Menu Map . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-6
Table 6-3. Display Menu Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-7
Table 6-4. Command Menu Operation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-10
Table 6-5. Typical System Status Messages . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-10
Table 7-1. Relay Card – MS and Industrial Relay Card IRC – MS Default Triggers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-2
Table 7-2. Relay Card - MS Contacts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-2
List of Tables
viii Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
This page intentionally left blank.
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 1-1
Chapter 1 Introduction
The Eaton®93E 40–60 kVA uninterruptible power supply (UPS) is a true online, continuous-duty,
transformerless, double-conversion, solid-state, three-phase system, providing conditioned and uninterruptible
AC power to protect the customer's load from power failures.
The Eaton 93E 40–60 kVA online power protection system is used to prevent loss of valuable electronic
information, minimize equipment downtime, and minimize the adverse effect on production equipment due to
unexpected power problems.
The Eaton 93E 40–60 kVA UPS continually monitors incoming electrical power and removes the surges, spikes,
sags, and other irregularities that are inherent in commercial utility power. Working with a building's electrical
system, the UPS system supplies clean, consistent power that sensitive electronic equipment requires for
reliable operation. During brownouts, blackouts, and other power interruptions, batteries provide emergency
power to safeguard operation.
The UPS is housed in a single free-standing cabinet, with safety shields behind the door for hazardous voltage
protection. Figure 1-1 shows the Eaton 93E 40–60 kVA UPS.
Figure 1-1. Eaton 93E UPS (40–60 kVA)
NOTE 1 Startup may be performed by the customer’s battery qualified electrical contractor
for single (not parallel) UPS installations without any accessory cabinets such as an
External Battery Cabinet.
NOTE 2 Startup and operational checks for parallel systems or installations with accessory
cabinets must be performed by an authorized Eaton Customer Service Engineer, or
the warranty terms specified on page W-1 become void. This service is offered as
part of the sales contract for the UPS. Contact an Eaton service representative in
advance (usually a two-week notice is required) to reserve a preferred startup date.
Introduction
1-2 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
1.1 UPS Standard Features
The UPS has many standard features that provide cost-effective and consistently reliable power protection. The
descriptions in this section provide a brief overview of the UPS standard features.
1.1.1 Installation Features
Power wiring can be routed to the back of the cabinet with connections made to easily accessible terminals.
Control wiring can be installed using conduit through the bottom of power terminal cover base or by routing
wiring through the power terminal cover base wiring channels and must be installed in accordance with Class 1
wiring methods.
1.1.2 Control Panel
The control panel, located on the front of the UPS, contains a liquid crystal display (LCD) and pushbutton
switches to control the operation of the UPS and to display the status of the UPS system. See Chapter 6, “UPS
Operating Instructions,” for additional information.
1.1.3 Customer Interface
lBuilding Alarm Monitoring – Up to three inputs in the UPS are available to connect the facility's alarm
system contacts. Some system configurations may limit the number of inputs available. The UPS uses
these inputs to monitor the building alarms in addition to the UPS status. See Chapter 7, “Communication,”
for additional information.
lMini-Slot Communication Bays – Two communication bays are standard equipment. One to two optional
Mini-Slot®connectivity cards can be installed in the UPS module at any time. Mini-Slot cards are quickly
installed at the rear of the UPS and are hot-pluggable. See Chapter 7, “Communication,” for additional
information.
1.1.4 High-Efficiency Normal Mode
The 93E Series UPS offers a High-Efficiency (HE) normal mode with double-conversion on demand that allows
the UPS to operate in standby bypass mode. This mode allows the 93E UPS to achieve 98% efficiency while
still protecting the load. High-efficiency mode is the default normal operating mode. See Chapter 6, “UPS
Operating Instructions,” for additional information.
1.1.5 Battery System
The battery system provides emergency short-term backup power to safeguard operation during brownouts,
blackouts, and other power interruptions. The battery system is equipped with lead-acid batteries.
The 93E–60/40 and 93E–60/60 UPS battery systems use internal batteries with External Battery Cabinet (EBC)
capability. Up to two Eaton 93E External Battery Cabinets (EBCs) can be added to UPS system. The EBCs are
connected in parallel with the internal batteries to provide extended run time.
The 93E-40 UPS (reduced battery sting model) battery system uses internal batteries only with no EBC
capability.
All UPSs in a parallel system must have the same battery configuration.
1.1.6 Advanced Battery Management
A three-stage charging system increases battery service life by optimizing recharge time, and protects batteries
from damage due to high current charging and inverter ripple currents. Charging at high currents can overheat
and damage batteries.
Introduction
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 1-3
1.2 Options and Accessories
Contact an Eaton sales representative for information about the following options.
1.2.1 External Battery Cabinet Capability
External battery cabinet capability provides the ability to add Eaton 93E EBCs to the UPS system in addition to
the internal batteries. An internal UPS battery breaker and external battery terminal block are added, along with
other internal parts allowing the connection of up to two EBCs.
1.2.2 External Battery Cabinet
Battery backup protection with additional runtime can be provide by equipping the UPS system with up to two
External Battery Cabinets (EBCs) containing sealed lead-acid, maintenance-free batteries. The EBCs are
available with four or six battery strings. Only EBC capable UPS systems can utilize EBCs. The EBCs are housed
in single, free-standing cabinets designed for line-up-and-match installation, but may be installed separate from
the UPS cabinet. The recommended installation location for adjacent battery cabinets is on the right side of the
UPS cabinet.
1.2.3 Integrated Accessory Cabinet-Distribution
The Integrated Accessory Cabinet-Distribution (IAC-D) provides power distribution with a 42-pole distribution
panel and up to three optional 3-pole 125A subfeed breakers. The IAC-D is housed in a single, free-standing
cabinet designed for line-up-and-match installation, but may be installed separate from the UPS cabinet. The
recommended installation location for an adjacent IAC-D is to the left of the UPS cabinet.
1.2.4 Sidecar Integrated Accessory Cabinet-Bypass
A Sidecar Integrated Accessory Cabinet-Bypass (SIAC-B) provides maintenance bypass functions. The SIAC-B
is available in a three breaker configuration enabling power to completely bypass the UPS. The UPS can then
be safely serviced or replaced without interrupting power to critical systems. A four breaker configuration is
available to provide a convenient method for removing power from the UPS when using the maintenance
bypass to supply the load. The SIAC-B is housed in a single cabinet designed to be attached directly to the
UPS cabinet. The SIAC-B can be ordered for installation on the left side or the right side of the UPS cabinet to
assist in integration with the overall system.
1.2.5 Integrated Transformer Cabinet
An single transformer Integrated Transformer Cabinet (ITC) provides three-phase 480 Vac input to three-phase
208Y/120 Vac output voltage transformation and isolation for input to the Eaton 93E UPS. An optional Dual
transformer ITC adds three-phase 208 Vac input to three-phase 480Y/277 Vac output voltage transformation
and isolation for output to the critical load. The ITC is housed in a single, free-standing cabinet designed for
line-up-and-match installation, but may be installed separate from the UPS cabinet. The recommended
installation location for an adjacent ITC is to the left of the UPS cabinet.
1.2.6 Integrated Accessory Cabinet-Tie
An Integrated Accessory Cabinet-Tie (IAC-T) provides the ability to parallel up to four UPSs together for
increased capacity and/or redundant capability. The IAC-T is housed in a single, free-standing cabinet designed
for line-up-and-match installation, but may be installed separate from the UPS cabinet. The recommended
installation location for an adjacent IAC-T is to the left of the UPS cabinet.
1.2.7 Integrated Accessory Cabinet-Tie and Bypass
An Integrated Accessory Cabinet-Tie and Bypass (IAC-TB) provides the ability to parallel two UPSs together for
increased capacity and/or redundant capability. In addition, maintenance bypass functions enable power to
completely bypass the UPS power module. The IAC-T is housed in a single, free-standing cabinet designed for
line-up-and-match installation, but may be installed separate from the UPS cabinet. The recommended
installation location for an adjacent IAC-T is to the left of the UPS cabinet.
Introduction
1-4 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
1.2.8 Reduced Battery String Model
The Eaton 93E-40 model is configured with six battery strings instead of eight to optimize the run time for
40 kVA with a subsequent reduction in cost and weight. Reduced battery string models are non-EBC capable.
If increased battery run time is required in the future, an extended run battery upgrade kit is available to increase
the internal battery system to eight strings.
The Eaton 93E-40 is also upgradable to full EBC capability with the addition of a 93E-40 to 93E–60/40 field
upgrade kit converting the Eaton 93E-40 to a Eaton 93E–60/40 or to an Eaton 93E–60/60 with a 93E-40 to
93E–60/60 field upgrade kit.
1.2.9 kVA Upgrades
The Eaton 93E–60/40 is firmware upgradable by an authorized Eaton Customer Service Engineer to an Eaton
93E–60/60.
1.2.10 Parallel System
A parallel UPS system with up to four UPSs can be installed to provide a parallel capacity and/or redundant
system. This load sharing system provides more capacity than a single UPS, and can provide backup,
depending on the load and configuration. In addition, when one UPS is taken out of service for maintenance or
is not operating properly, a redundant UPS continues to supply uninterrupted power to the critical load. A
Controller Area Network (CAN) provides connectivity for system metering and operational mode control. The
parallel system consists of two to four UPSs each with a parallel CAN, and either a IAC-T or IAC-TB to act as a
tie point and to control the output.
1.2.11 Monitoring and Communication
Mini-Slot Cards – Optional Mini-Slot® cards support several protocols, such as SNMP, HTTP, Modbus® and
RS232.
See Chapter 7, “Communication,“ for additional information on monitoring and communication features.
1.2.12 Dual Feed
Optional dual-feed input terminals are available to provide a separate bypass feed to the UPS.
1.3 Basic System Configurations
The following basic UPS system configurations are possible:
lSingle UPS with reduced string internal batteries
lSingle UPS with internal batteries and EBC capability
lSingle UPS with internal batteries, EBC capability, and one or two external battery cabinets
lSingle UPS with reduced string internal batteries and accessory cabinets
lSingle UPS with internal batteries, EBC capability, and accessory cabinets
lSingle UPS with internal batteries, EBC capability and one or two external battery cabinets and accessory
cabinets
The UPS system configuration can be enhanced by adding optional accessories such as a Remote Emergency
Power-off (REPO) control or Mini-Slot communication cards.
NOTE 1 All UPSs in a parallel system must have the same battery configuration.
NOTE 2 The SIAC-B cannot be used in a parallel system.
Introduction
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 1-5
1.4 Using This Manual
This manual describes how to install and operate the Eaton 93E 40–60 kVA. Read and understand the
procedures described in this manual to ensure trouble-free installation and operation. In particular, be
thoroughly familiar with the REPO procedure (see paragraph 6.3.11).
The information in this manual is divided into sections and chapters. The system, options, and accessories
being installed dictate which parts of this manual should be read. At a minimum, Chapters 1 through 4
and Chapter 6 should be examined.
Read through each procedure before beginning the procedure. Perform only those procedures that apply to the
UPS system being installed or operated.
1.5 Conventions Used in This Manual
This manual uses these type conventions:
lBold type highlights important concepts in discussions, key terms in procedures, and menu options, or
represents a command or option that you type or enter at a prompt.
lItalic type highlights notes and new terms where they are defined.
lScreen type represents information that appears on the screen or LCD.
In this manual, the term UPS refers only to the UPS cabinet and its internal elements. The term UPS system
refers to the entire power protection system – the UPS cabinet, an external battery system, and options or
accessories installed.
1.6 Symbols, Controls, and Indicators
The following are examples of symbols used on the UPS or accessories to alert you to important information:
Icon Description
Note Information notes call attention to important features or instructions.
[Keys] Brackets are used when referring to a specific key, such as [Enter] or [Ctrl].
RISK OF ELECTRIC SHOCK - Observe the warning associated with the risk
of electric shock symbol.
CAUTION: REFER TO OPERATOR'S MANUAL - Refer to your operator's
manual for additional information, such as important operating and
maintenance instructions.
This symbol indicates that you should not discard the UPS or the UPS
batteries in the trash. This product contains sealed, lead-acid batteries and
must be disposed of properly. For more information, contact your local
recycling/reuse or hazardous waste center.
This symbol indicates that you should not discard waste electrical or
electronic equipment (WEEE) in the trash. For proper disposal, contact your
local recycling/reuse or hazardous waste center.
Introduction
1-6 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
1.7 For More Information
Refer to the Eaton 93E External Battery Cabinet Installation Manual for the following additional information:
lInstallation instructions, including site preparation, planning for installation, wiring and safety information,
and detailed illustrations of cabinets with dimensional and connection point drawings
Refer to the Eaton 93E Integrated Accessory Cabinet-Distribution Installation and Operation Manual for the
following additional information:
lInstallation instructions, including site preparation, planning for installation, wiring and safety information,
and detailed illustrations of cabinets with dimensional and connection point drawings
lOperation, including breakers, standard features and optional accessories, procedures for using the tie and
bypass functions, and information about maintenance
Refer to the Eaton 93E Integrated Transformer Cabinet Installation Manual for the following additional
information:
lInstallation instructions, including site preparation, planning for installation, wiring and safety information,
and detailed illustrations of cabinets with dimensional and connection point drawings
Refer to the Eaton 93E Integrated Accessory Cabinet-Tie and Bypass Installation and Operation Manual for the
following additional information:
lInstallation instructions, including site preparation, planning for installation, wiring and safety information,
and detailed illustrations of cabinets with dimensional and connection point drawings
lOperation, including breakers, standard features and optional accessories, procedures for using the tie and
bypass functions, and information about maintenance
Refer to the Eaton 93E Sidecar Integrated Accessory Cabinet-Bypass Installation and Operation Manual for the
following additional information:
lInstallation instructions, including site preparation, planning for installation, wiring and safety information,
and detailed illustrations of cabinets with dimensional and connection point drawings
Operation, including breakers, standard features and optional accessories, procedures for using the tie and
bypass functions, and information about maintenance
Visit www.eaton.com/powerquality or contact an Eaton service representative for information on how to obtain
copies of these manuals.
1.8 Getting Help
If help is needed with any of the following:
lScheduling initial startup
lRegional locations and telephone numbers
lA technical question about any of the information in this manual
lA question this manual does not answer
Please call the Customer Reliability Center at:
United States: 1-800-843-9433
Canada: 1-800-461-9166 ext 260
All other countries: Call your local service representative
Please use the following e-mail address for manual comments, suggestions, or to report an error in this manual:
E-ESSDocumentation@eaton.com
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 2-1
Chapter 2 Safety Warnings
IMPORTANT SAFETY INSTRUCTIONS SAVE THESE INSTRUCTIONS
This manual contains important instructions that should be followed during installation and
maintenance of the UPS and batteries. Read all instructions before operating the equipment and
save this manual for future reference.
The UPS is designed for industrial or computer room applications, and contains safety shields
behind the door and front panels. However, the UPS is a sophisticated power system and should
be handled with appropriate care.
DANGER
This UPS contains LETHAL VOLTAGES. All repairs and service should be performed by
AUTHORIZED SERVICE PERSONNEL ONLY. There are NO USER SERVICEABLE PARTS inside the
UPS.
WARNING
lThe UPS is powered by its own energy source (batteries). The output terminals may carry live
voltage even when the UPS is disconnected from an AC source.
lTo reduce the risk of fire or electric shock, install this UPS in a temperature and humidity
controlled, indoor environment, free of conductive contaminants. Ambient temperature must
not exceed 30C (86F). Do not operate near water or excessive humidity (95% maximum). The
system is not intended for outdoor use.
lAs a result of the connected loads high leakage current is possible. Connection to earth ground
is required for safety and proper product operation. Do not check UPS operation by any action
that includes removal of the earth (ground) connection with loads attached.
lEnsure all power is disconnected before performing installation or service.
lBatteries can present a risk of electrical shock or burn from high short-circuit current. The
following precautions should be observed: 1) Remove watches, rings, or other metal objects;
2) Use tools with insulated handles; 3) Do not lay tools or metal parts on top of batteries;
4) Wear rubber gloves and boots.
lELECTRIC ENERGY HAZARD. Do not attempt to alter any UPS or battery wiring or connectors.
Attempting to alter wiring can cause injury.
lDo not open or mutilate batteries. Released electrolyte is harmful to the skin and eyes. It may
be toxic.
CAUTION
lInstallation or servicing should be performed by qualified service personnel knowledgeable of
UPS and battery systems, and required precautions. Keep unauthorized personnel away from
equipment. Consider all warnings, cautions, and notes before installing or servicing equipment.
DO NOT DISCONNECT the batteries while the UPS is in Battery mode.
lReplace batteries with the same number and type of batteries as originally installed with the
UPS.
lDisconnect the charging source prior to connecting or disconnecting terminals.
Safety Warnings
2-2 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
lDetermine if the battery is inadvertently grounded. If it is, remove the source of the ground.
Contacting any part of a grounded battery can cause a risk of electric shock. An electric shock is
less likely if you disconnect the grounding connection before you work on the batteries.
lProper disposal of batteries is required. Refer to local codes for disposal requirements.
lDo not dispose of batteries in a fire. Batteries may explode when exposed to flame.
lKeep the UPS door closed and front panels installed to ensure proper cooling airflow and to
protect personnel from dangerous voltages inside the unit.
lDo not install or operate the UPS system close to gas or electric heat sources.
lLead-acid batteries can present a risk of fire because they generate hydrogen gas. Do not
smoke when near batteries. Do not cause flame or spark in battery area. Discharge static
electricity from body before touching batteries by first touching a grounded metal surface.
lThe operating environment should be maintained within the parameters stated in this manual.
lKeep surroundings uncluttered, clean, and free from excess moisture.
lObserve all DANGER, CAUTION, and WARNING notices affixed to the inside and outside of the
equipment.
AVERTISSEMENT!
lLes batteries peuvent présenter un risque de décharge électrique ou de brûlure par des
courts–circuits de haute intensité. Prendre les précautions nécessaires.
lPour le replacement, utiliser le même nombre et modéle des batteries.
ATTENTION!
lUne mise au rebut réglementaire des batteries est obligatoire. Consulter les règlements en
vigueur dans votre localité.
lNe jamais jeter les batteries au feu. L'exposition aux flammes risque de les faire exploser.
lLes accumulateurs au plomb-acide peuvent représenter un risque d’incendie, car ils génèrent
de l’hydrogène gazeux. Ne pas fumer près des accumulateurs. Ne pas produire de flamme ou
d’étincelle dans la zone de l’accumulateur. Dissiper l'électricité statique de votre corps en
touchant une surface reliée à la terre avant de toucher les accumulateurs.
Section 1
Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 3-1
Chapter 3 UPS Installation Plan and Unpacking
Use the following basic sequence of steps to install the UPS:
1. Create an installation plan for the UPS system (Chapter 3).
2. Prepare your site for the UPS system (Chapter 3).
3. Inspect and unpack the UPS cabinet (Chapter 3).
4. Unload and install the UPS cabinet, and wire the system (Chapter 4).
5. Install features, accessories, or options, as applicable (Chapter 4).
6. Complete the Installation Checklist (Chapter 4).
7. Have authorized service personnel perform preliminary operational checks and start up the system.
3.1 Creating an Installation Plan
Before installing the UPS system, read and understand how this manual applies to the system being installed.
Use the procedures and illustrations in paragraph 3.2 and Chapter 4 to create a logical plan for installing the
system.
3.2 Preparing the Site
For the UPS system to operate at peak efficiency, the installation site should meet the environmental
parameters outlined in this manual. The operating environment must meet the weight, clearance, and
environmental requirements specified.
3.2.1 Environmental and Installation Considerations
The UPS system installation must meet the following guidelines:
lThe system must be installed on a level floor suitable for computer or electronic equipment.
lThe system must be operated at an altitude no higher than 1500m (5000 ft) without derating. See Table 3-1
for altitude and thermal derating requirements. For additional assistance with high altitude operation,
contact an Eaton service representative (see paragraph 1.7).
lThe system must be installed in a temperature and humidity controlled indoor area free of conductive
contaminants.
Failure to follow guidelines may void your warranty.
NOTE 1 Startup may be performed by the customer’s battery qualified electrical contractor
for single (not parallel) UPS installations without any accessory cabinets such as an
External Battery Cabinet.
NOTE 2 Startup and operational checks for parallel systems or installations with accessory
cabinets must be performed by an authorized Eaton Customer Service Engineer, or
the warranty terms specified on page W-1 become void. This service is offered as
part of the sales contract for the UPS. Contact an Eaton service representative in
advance (usually a two-week notice is required) to reserve a preferred startup date.
UPS Installation Plan and Unpacking
3-2 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
The basic environmental requirements for operation of the UPS are:
lAmbient Temperature Range: 0–30C (32–86F)
lRecommended Operating Range: 20–25C (68–77F)
lMaximum Relative Humidity: 95%, noncondensing
CAUTION
If battery systems are located in the same room as the UPS, the battery manufacturer's
environmental requirements should be followed if they are more stringent than the UPS
requirements. Operating temperatures above the recommended range will result in decreased
battery life and performance, and may reduce or void the battery warranty.
The UPS ventilation requirements are shown in Table 3-2.
Table 3-1. Combined Altitude and Thermal Derating Factors
Altitude
Meters (Feet)
Derating Factor
40°C Ambient 35°C Ambient 30°C Ambient 25°C Ambient
1000 (3300) 0.82 0.91 — —
1500 (5000) 0.78 0.86 1.00 —
2000 (6600) 0.74 0.82 0.95 —
2500 (8300) 0.70 0.78 0.91 1.00
3000 (10000) 0.67 0.74 0.86 0.95
3500 (11600) 0.63 0.70 0.82 0.91
4000 (13200) 0.59 0.67 0.78 0.86
4500 (15000) 0.54 0.63 0.74 0.82
5000 (16500) 0.50 0.59 0.70 0.78
NOTE Altitude derating based on interpolation of IEC 62040-3 Ed1.
Thermal derating based on thermal testing in accordance with UL 60950.
Table 3-2. Air Conditioning or Ventilation Requirements During Full Load Operation
Model Rating Input Voltage Output Voltage
Heat Rejection
BTU/hr x1000 (kg-cal/hr)
Minimum Required
Cooling Air Flow
Eaton 93E-40 40 kVA 208/220 208/220 9.29 (2342) 292 liters/sec (618 cfm)Eaton 93E–60/40
Eaton 93E–60/60 60 kVA 208/220 208/220 13.94 (3513)
UPS Installation Plan and Unpacking
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 3-3
The UPS equipment operating environment must meet the weight requirements shown in Table 3-3 and the
size requirements shown in Figure 3-1 through Figure 3-4. Dimensions are in millimeters (inches).
The UPS cabinet uses forced air cooling to regulate internal component temperature. Air inlets are in the front
of the cabinet and outlets are in the back of the cabinet. Allow clearance in front of and in back of the cabinet
for proper air circulation. The clearances required around the UPS cabinet are shown in Table 3-4.
Table 3-3. UPS Cabinet Weights
Model
Weight
kg (lb)
Shipping Installed Point Loading
Eaton 93E-40 with internal batteries 675 (1488) 590 (1301) 8 at 74 (163)
Eaton 93E–60/40 with internal batteries 765 (1686) 680 (1499) 8 at 85 (187)
Eaton 93E–60/60 with internal batteries
Eaton 93E-40 without batteries
405 (892) Not Applicable Not ApplicableEaton 93E–60/40 without batteries
Eaton 93E–60/60 without batteries
Table 3-4. UPS Cabinet Clearances
From Top of Cabinet 304.8 mm (12") working space
From Front of Cabinet 914.4 mm (36") working space
From Front of Cabinet Minimum 650 mm (25.6") for cooling air intake and door swing
Recommended 914.4 mm (36") working space
From Back of Cabinet Minimum of 203.2 mm (8”) for operation
Recommended 914.4 mm (36") for service
Clearances must comply with all applicable national and local codes. Flexible
conduit may be used to adjust between required operation and service clearances.
From Right Side of Cabinet None Required
From Left Side of Cabinet None Required
UPS Installation Plan and Unpacking
3-4 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 3-1. UPS Cabinet Dimensions (Front and Right Side Views)
Dimensions are in millimeters [inches]
Front
Right Side
Back
UPS Installation Plan and Unpacking
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 3-5
Figure 3-2. UPS Cabinet Dimensions (Top and Bottom Views)
Front
Front
Top Bottom
Dimensions are in millimeters [inches]
UPS Installation Plan and Unpacking
3-6 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 3-3. UPS Cabinet Center of Gravity
CG
Dimensions are in millimeters [inches]
Weight and Center of Gravity
ABC
Weight
kg (lb)
With Batteries (93E-40 – 6 Strings) 815 (32.1) 300 [11.8] 399 (15.7) 590 (1301) – Installed
With Batteries (93E–60/40 and 93E–60/60 – 8 Strings) 785 [30.9] 300 [11.8] 399 [15.7] 680 (1499) – Installed
Without Batteries 985 [38.8] 300 [11.8] 399 [15.7] 405 (892) – Shipping
UPS Installation Plan and Unpacking
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 3-7
Figure 3-4. Remote EPO Switch Dimensions
3.2.2 UPS System Power Wiring Preparation
Read and understand the following notes while planning and performing the installation:
WARNING
As a result of the connected loads high leakage current is possible. Connection to earth ground is
required for safety and proper product operation. Do not check UPS operation by any action that
includes removal of the earth (ground) connection with loads attached.
lRefer to national and local electrical codes for acceptable external wiring practices.
lTo allow for future kVA upgrades, consider installing a derated UPS using wiring and external overcurrent
protection breakers sized for a fully rated UPS.
lFor external wiring, use 90°C copper wire. Wire sizes listed in Table 3-5 are for copper wiring only. If wire is
run in an ambient temperature greater than 30°C, higher temperature wire and/or larger size wire may be
necessary. Wire sizes are based on using the specified breakers.
lWire ampacities are chosen from Table 310-16 of the National Electrical Code® (NEC®). Specification is for
copper wire with a 90°C rating.
lMaterial and labor for external wiring requirements are to be supplied by designated personnel.
lIf installing an external maintenance bypass, all feeds to the UPS including the Rectifier Input Breaker (RIB)
(if installed) must have a service disconnect independent of the maintenance bypass power path. Most
maintenance bypass solutions provide UPS input feeds derived from but isolated from the maintenance
bypass power path. If the maintenance bypass solution being installed does not provide such functionality,
DO NOT use a single feeder breaker to supply both the UPS and the maintenance bypass.
115.8
[4.56]
114.3
[4.50]
0.87
[0.22] 88.9
[3.50]
1.57
[0.40]
95.3
[3.57]
Front View
1/2" Knockout Pattern
(Typical 5 Sides
Needed to
remove key
(Square)
Dimensions are in millimeters [inches]
UPS Installation Plan and Unpacking
3-8 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
lPhase rotation must be clockwise starting with phase A (rotation A,B,C).
lThe bypass feed into this equipment uses four wires. The rectifier feed into this equipment uses four wires.
The phases must be symmetrical about ground (from a Wye source, phase rotation clockwise A, B, C) for
proper equipment operation.
lParallel UPS input wiring size requirements and output wiring size requirements from the UPSs to the
Integrated Accessory Cabinet-Tie (IAC-T) or Integrated Accessory Cabinet-Tie and Bypass (IAC-TB) are the
same as listed in Table 3-5. Refer to the Eaton 93E Integrated Accessory Cabinet-Tie and Bypass Installation
and Operation Manual listed in paragraph 1.7 for additional IAC-T or IAC-TB wiring and termination
requirements.
UPS Installation Plan and Unpacking
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 3-9
For external wiring requirements, including the minimum AWG size of external wiring, see Table 3-5. Wire sizes
listed are for copper wiring only. The number of neutral conductors listed are for single size neutral wiring.
A 1.5x sized neutral can be supported by this product. Two terminal landings are provided to accommodate
extra neutral wiring.
Table 3-5. Input/Output Ratings and External Wiring Requirements for the Eaton 93E-40, 93E–60/40, and 93E–60/60
Basic Unit Rating
Units Rating 50/60 Hz
kVA
kW
40
32
60
48
Input Voltage Volts 208/220 208/220
Output Voltage Volts 208/220 208/220
AC Input to UPS Rectifier (0.98 Minimum pF)
Full load current plus battery recharge current
(3) Phases, (1) Neutral, (1) Ground A
Amps 128/121 185/181
Minimum Conductor Size (Phase A, B, and C)
Number per Phase
AWG or kcmil
(each)
2/0
(1)
250
(1)
Minimum Conductor Size (Neutral)
Number per Phase
–AWG or kcmil
(each)
2/0
(1)
250
(1)
Minimum Conductor Size (Ground)
Number per Phase
–AWG or kcmil
(each)
4
(1)
2
(1)
AC Input to UPS Bypass (Five Wire, Dual-Feed)
Full Load Current
(3) Phases, (1) Neutral, (1) Ground B
Amps 111/105 167/157
Minimum Conductor Size (Phase A, B, and C)
Number per Phase
AWG or kcmil
(each)
2/0
(1)
250
(1)
Minimum Conductor Size (Neutral)
Number per Phase
–AWG or kcmil
(each)
2/0
(1)
250
(1)
Minimum Conductor Size (Ground)
Number per Phase
–AWG or kcmil
(each)
4
(1)
2
(1)
DC Input from External Battery
(1) Positive, (1) Negative, (1) Ground C
Total Amps 165 248
Minimum Conductor Size (Phase Positive and Negative)
Number per Pole
AWG or kcmil
(each)
3/0
(1)
1/0
(2)
Minimum Conductor Size (Ground)
Number per Phase
–AWG or kcmil
(each)
4
(1)
2
(1)
AC Output to Critical Load (Five Wire)
Full Load Current
(3) Phases, (1) Neutral, (1) Ground D
Amps 111/105 167/157
Minimum Conductor Size (Phase A, B, and C)
Number per Phase
AWG or kcmil
(each)
2/0
(1)
250
(1)
Minimum Conductor Size (Neutral)
Number per Phase
–AWG or kcmil
(each)
2/0
(1)
250
(1)
Minimum Conductor Size (Ground)
Number per Phase
–AWG or kcmil
(each)
4
(1)
2
(1)
NOTE Callout letters A, B, and D map to Figure 5-5. Callout letters A, B, C, and D map to Figure 5-6 and Figure 5-7.
UPS Installation Plan and Unpacking
3-10 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
The power wiring terminals are pressure terminations, UL and CSA rated at 90°C. See Table 3-6 for external
power cable terminations.
Figure 4-7 and Figure 4-8 show the location of the UPS power cable terminals.
Table 3-6. UPS External Power Cable Terminations for the Eaton 93E-40, 93E–60/40, and 93E–60/60
Terminal Function Terminal Function
Number and Size of Pressure
Termination
AWG or kcmil
Tightening Torque
Nm (lb in) Screw Size and Type
AC Input to UPS Rectifier L1 Phase A 1 – #6-250 22.6 (200) 1/4 in. Hex
L2 Phase B 1 – #6-250 22.6 (200) 1/4 in. Hex
L3 Phase C 1 – #6-250 22.6 (200) 1/4 in. Hex
N Neutral 2 – #6-250 22.6 (200) 1/4 in. Hex
AC Input to Bypass L1 Phase A 1 – #6-250 22.6 (200) 1/4 in. Hex
L2 Phase B 1 – #6-250 22.6 (200) 1/4 in. Hex
L3 Phase C 1 – #6-250 22.6 (200) 1/4 in. Hex
N Neutral 2 – #6-250 22.6 (200) 1/4 in. Hex
AC Output to Critical Load L1 Phase A 1 – #6-250 22.6 (200) 1/4 in. Hex
L2 Phase B 1 – #6-250 22.6 (200) 1/4 in. Hex
L3 Phase C 1 – #6-250 22.6 (200) 1/4 in. Hex
N Neutral 2 – #6-250 22.6 (200) 1/4 in. Hex
DC Input from External Battery + Battery (+) 2 – #6-250 22.6 (200) 1/4 in. Hex
– Battery (-) 2 – #6-250 22.6 (200) 1/4 in. Hex
Customer Ground Ground Ground 4 – #6-300 31.1 (275) 5/16 in. Hex
NOTE Customer ground, sized in accordance with NEC Table 250.122, can be run in any conduit listed in Table 3-7.
UPS Installation Plan and Unpacking
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 3-11
Conduit sizes were chosen from NEC Table 4, Electrical Metallic Tubing (EMT). See Table 3-7 for conduit
requirements.
Per NEC article 300, 3(B)(1), all three-phase conductors must be run in the same conduit. Neutral and ground
must be run in the same conduit as the phase conductors.
Conduit is sized to accommodate one neutral conductor the same size as the phase conductor and one ground
conductor sized in accordance with NEC Table 250.122.This product can support a 1.5x sized neutral. If two
neutral conductors or an oversized neutral conductor are to be installed, verify the size of the conduit needed
to accommodate the extra wire or size and use that conduit size in place of the conduit size listed in Table 3-7.
Conduit sizes listed are for copper wiring only.
External overcurrent protection and disconnect are not provided by this product, but are required by codes.
Refer to Table 3-5 for wiring requirements. If an output lockable disconnect is required, it is to be supplied by
the customer.
Table 3-8 lists the recommended rating for input circuit breakers.
CAUTION
To reduce the risk of fire, connect only to a circuit provided with maximum input
circuit breaker current ratings from Table 3-8 in accordance with the NEC, ANSI/NFPA 70.
Table 3-7. Power Cable Conduit Requirements
UPS Model Voltage Terminal
Number of Wires
in Conduit
Minimum Conduit
Trade Size
Number of
Conduits
Eaton 93E-40
Eaton 93E–60/40
208/220 Vac AC Input to UPS Rectifier
(A, B, C, Neutral, Ground)
52 1
AC Input to Bypass and Output (Five Wire)
(A, B, C, Neutral, Ground)
52 1
DC Battery
(Positive, Negative, Ground)
31-1/2 1
Eaton 93E–60/60 208 /220Vac AC Input to UPS Rectifier
(A, B, C, Neutral, Ground)
52-1/2 1
AC Input to Bypass and Output (Five Wire)
(A, B, C, Neutral, Ground)
52-1/2 1
DC Battery
(Positive, Negative, Ground)
32 1
Table 3-8. Recommended Input Circuit Breaker Ratings
Input Rating
UPS Model Load Rating 208/220V
Eaton 93E-40
Eaton 93E–60/40
80% Rated 175A
100% Rated 150A
Eaton 93E–60/60 80% Rated 250A
100% Rated 200A
UPS Installation Plan and Unpacking
3-12 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
The line-to-line unbalanced output capability of the UPS is limited only by the full load per phase current values
for AC output to critical load shown in Table 3-5. The recommended line-to-line load unbalance is 50% or less.
Bypass and output overcurrent protection and bypass and output disconnect switches are to be supplied by
the customer. Table 3-9 lists the recommended rating for bypass and output circuit breakers.
Battery voltage is computed at 2 volts per cell as defined by Article 480 of the NEC. Rated battery current is
computed based on 2 volts per cell.
3.2.3 UPS System Interface Wiring Preparation
Control wiring for features and options should be connected at the customer interface terminal blocks located
inside the UPS.
WARNING
Do not directly connect relay contacts to the mains related circuits. Reinforced insulation to the
mains is required.
Read and understand the following notes while planning and performing the installation:
lUse Class 1 wiring methods (as defined by the NEC) for interface wiring from 30V to 600V. The wire should
be rated for 600V, 1A minimum. 12 AWG maximum wire size.
lUse Class 2 wiring methods (as defined by the NEC) for interface wiring up to 30V. The wire should be rated
for 24V, 1A minimum.
lBecause of the REPO and building alarm wiring route in the UPS cabinet, the wire should be rated for a
minimum of 300V.
lUse twisted-pair wires for each input and return or common.
lAll interface wiring and conduit is to be supplied by the customer.
lWhen installing external interface wiring between a REPO or building alarm and the UPS interface terminals,
conduit must be installed between each device and the UPS cabinet.
lInterface wiring can be installed using conduit through the bottom of power terminal cover base or by
routing wiring through the power terminal cover base wiring channels between the UPS and SIAC-B, IAC-T,
or IAC-TB.
lIf using the power terminal wiring channel, keep interface wiring separate from power wiring or use
shielded wire.
lIf using conduit, install the interface wiring in separate conduit from the power wiring.
lAll building alarm inputs require an isolated normally-open contact or switch (rated at 24 Vdc, 20 mA
minimum) connected between the alarm input and common terminal. All control wiring and switch contacts
are customer-supplied.
lLAN and telephone drops for use with Mini-Slot connectivity cards must be supplied by the customer.
Table 3-9. Recommended Bypass and Output Circuit Breaker Ratings
Output Rating
UPS Model Load Rating 208/220V
Eaton 93E-40
Eaton 93E–60/40
80% Rated 175A
100% Rated 150A
Eaton 93E–60/60 80% Rated 250A
100% Rated 200A
UPS Installation Plan and Unpacking
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 3-13
lThe REPO feature opens all switchgear in the UPS cabinet and isolates power from your critical load. Local
electrical codes may also require tripping upstream protective devices to the UPS.
lThe REPO switch must be a latching-type switch not tied to any other circuits.
lA jumper wire must be connected between pins 3 and 4 on the REPO terminal block if using a
normally-closed REPO switch.
lREPO wiring should be a minimum of 22 AWG and a maximum of 14 AWG.
lThe REPO switch wiring must be in accordance with NEC Article 725 Class 2 requirements.
lThe maximum distance between the REPO and the UPS cannot exceed 150 meters (500 feet).
3.3 Battery Type
The battery types listed in Figure 3-10 are supplied in the UPS Cabinet and external Battery Cabinet. When
purchasing UPS Cabinet or external Battery Cabinet without batteries, only the following types are
recommended. Use of any other battery type inside Eaton cabinets will void the product warranty. When
replacing batteries use the same manufacturer and part number originally supplied with the unit to ensure
correct harness fit and terminal landing.
3.4 Inspecting and Unpacking the UPS Cabinets
The cabinet is shipped bolted to a wooden pallet and protected with an outer wood container (see Figure 3-5).
WARNING
The UPS cabinet is heavy (see Table 3-3). If unpacking and unloading instructions are not closely
followed, the cabinet may tip and cause serious injury.
1. Carefully inspect the outer packaging for evidence of damage during transit.
CAUTION
Do not install a damaged cabinet. Report any damage to the carrier and contact an Eaton service
representative immediately.
2. Use a forklift or pallet jack to move the packaged cabinet to the installation site, or as close as possible,
before unpacking. If possible, move the cabinets using the pallet. Insert the forklift or pallet jack forks
between the supports on the bottom of the pallet (see Figure 3-3 for the UPS cabinet center of gravity
measurements).
Table 3-10. Battery Type
Battery Manufacturer CSB Battery Technologies Inc. G.S. Yuasa
Battery Model HRL1234WF2FR REW45-12FR
Battery Quantity 93E-40 108 108
Battery Quantity 93E–60/40 144 144
Battery Quantity 93E–60/60 144 144
NOTE For the following step, verify that the forklift or pallet jack is rated to handle the
weight of the cabinet (see Table 3-3 for cabinet weight).
UPS Installation Plan and Unpacking
3-14 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
CAUTION
Do not tilt the UPS cabinets more than 10° from vertical or the cabinets may tip over.
3. Set the pallet on a firm, level surface, allowing a minimum clearance of 3m (10 ft) on each side for
removing the cabinet from the pallet.
4. Remove the protective wood container from the cabinet:
a. Straighten the tabs securing the top panel of the wooden container to the side panels of the
container.
b. Remove the top panel and retain for later use as a ramp in unloading the cabinet from the pallet.
c. Straighten the tabs securing the side panels of the container to the front and back panels of the
container.
d. Remove the side panels.
e. Straighten the tabs securing the front and back panels of the container to the bottom of the container.
f. Remove the front and back panels.
5. Remove the inner protective packaging. Retain the parts kit box, ramp brackets, and ramp extension
packed at the top of the cabinet.
6. Recycle the remainder of the outer shipping container and the inner protective packaging in a responsible
manner.
7. Inspect the contents for any evidence of physical damage, and compare each item with the Bill of Lading.
If damage has occurred or shortages are evident, contact an Eaton service representative immediately to
determine the extent of the damage and its impact on further installation.
NOTE For the following steps, use pincer type pliers or a large flat blade screw driver to
straighten the securing tabs.
NOTE While waiting for installation, protect the unpacked cabinet from moisture, dust, and
other harmful contaminants. Failure to store and protect the UPS properly may void
your warranty.
UPS Installation Plan and Unpacking
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 3-15
Figure 3-5. UPS Cabinet as Shipped on Pallet (wood container removed)
UPS Installation Plan and Unpacking
3-16 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
This page intentionally left blank.
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-1
Chapter 4 UPS System Installation
4.1 Preliminary Installation Information
WARNING
Installation should be performed only by qualified personnel.
Refer to the following while installing the UPS system:
lChapter 3 for cabinet dimensions, equipment weight, wiring and terminal data, and installation notes.
lDo not tilt the cabinets more than ±10 during installation.
lIf perforated floor tiles are required for ventilation, place them in front of the UPS.
4.2 Unloading the UPS Cabinet from the Pallet
The UPS Cabinet is bolted to a wooden pallet supported by wood skids. To remove the pallet:
WARNING
The UPS cabinet is heavy (see Table 3-3). If unpacking and unloading instructions are not closely
followed, the cabinet may tip and cause serious injury.
CAUTION
lDo not tilt cabinet more than 10° from vertical.
lLift the cabinets only with a forklift or damage may occur.
1. If not already accomplished, use a forklift or pallet jack to move the UPS cabinet to the installation area, or
as close as possible, before unloading from the pallet. Insert the forklift or pallet jack forks between the
supports on the bottom of the pallet (see Figure 3-3 for the UPS cabinet center of gravity measurements).
2. Remove four bolts securing the front shipping bracket to the cabinet and four bolts securing the bracket to
the pallet (see Figure 4-1). Remove the front shipping bracket. If installing the cabinet permanently, retain
the shipping bracket and securing hardware for later use.
3. Attach the ramp to the front of the pallet (see Figure 4-2):
a. Locate the ramp (top panel from wood container), ramp extension, and ramp brackets with M10 bolts.
b. Place the ramp against the front of the pallet.
c. Secure the ramp to pallet using the supplied ramp brackets and M10 bolts. Insert the lip on the
brackets into the slots at the top of the ramp. Use the existing holes in the pallet to secure the ramp
brackets.
d. Attach the ramp extension to the front of the ramp by inserting the tabs on the extension into the
slots at the bottom of the ramp.
4. If the leveling feet are not fully retracted, turn the leveling feet until they are retracted.
NOTE For the following steps, verify that the forklift or pallet jack is rated to handle the
weight of the cabinet (see Table 3-3 for cabinet weight)
UPS System Installation
4-2 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 4-1. Removing the Front Shipping Bracket
5. Remove four bolts securing the rear shipping bracket to the cabinet and four bolts securing the bracket to
the pallet (see Figure 4-3). Remove the rear shipping bracket. If installing the cabinet permanently, retain
the shipping bracket and securing hardware for later use.
WARNING
Do not stand directly in front of the pallet while unloading the cabinet. If unloading instructions are
not closely followed, the cabinet may cause serious injury.
6. Slowly roll the cabinet toward the front of the pallet. Continue rolling the cabinet down the ramp until the
cabinet is clear of the ramp (see Figure 4-4).
7. Roll the cabinet to the final installation location.
Front Door
Front Shipping Bracket
Shipping Bracket
Bolts
Shipping Bracket
Bolts
Pallet
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-3
8. If installing the cabinet permanently, retain the shipping brackets and hardware; otherwise, recycle the
pallet, ramp, and shipping brackets in a responsible manner.
9. Secure the UPS cabinet in position by lowering the leveling feet until the cabinet is not resting on the
casters and the cabinet is level.
10. If permanently mounting the system, proceed to Step 11; otherwise, continue to Step 13.
11. Using the retained hardware, reinstall the shipping brackets removed in Step 2 and Step 5 to the front and
rear of the UPS cabinet with the angle facing outward (see Figure 4-1 and Figure 4-3).
12. Secure the cabinet to the floor with customer-supplied hardware.
13. Proceed to paragraph 4.3.
Figure 4-2. Attaching the Ramp to the Pallet
Ramp Extension
Pallet
UPS
Cabinet
Ramp
(top panel from
wood container)
Metal Tab
(2 places)
Ramp Bracket
and M10 bolt
(2 places)
UPS System Installation
4-4 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 4-3. Removing the Rear Shipping Bracket
Rear Shipping Bracket
Shipping Bracket
Bolts
Shipping Bracket
Bolts
Pallet
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-5
Figure 4-4. Rolling the Cabinet Down the Ramp
UPS System Installation
4-6 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
4.3 Installing Power Terminal Cover Base
To install the Power Terminal Cover Base:
1. Locate the terminal cover base (see Figure 4-5) from the parts kit.
2. If installing wiring using conduit, proceed to Step 3; otherwise, proceed to Step 4.
3. Punch or drill holes in the bottom of the power terminal cover base (see 4-5 and 4-6) for the AC input,
output, bypass, DC input, REPO conduit as required.
4. Using the hardware provided, install the terminal cover base to the back panel of the UPS using the
existing cabinet screw holes (see Figure 4-6).
5. Proceed to paragraph 4.4.
Figure 4-5. UPS Power Terminal Cover Parts
NOTE Wiring can be installed between the UPS and accessory cabinets by using conduit
or by routing wiring through the power terminal cover base wiring channels.
Right Side
Left Side
Top
Base
Conduit Landing for AC Input, Output,
and Bypass, DC Input, and REPO.
(Install conduit to bottom of plate.)
Wire Hooks
Base (Inside View)
NOTE Do not install the Power Terminal Cover Left and/or Right Side covers if wiring adjacent ancillary cabinets
(such as an EBC or IAC) using the power terminal base wiring channel.
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-7
Figure 4-6. UPS Power Terminal Cover Base Installation and Conduit Landing Wire Entry Locations
Conduit Landing for AC Input, Output,
and Bypass, DC Input, and REPO.
(Install conduit to bottom of plate.)
Power Terminal Cover
Base Installed
Back
UPS System Installation
4-8 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
4.4 External Battery Cabinet Installation
If installing External Battery Cabinets (EBCs), refer to the Eaton 93E External Battery Cabinet Installation
Manual listed in paragraph 1.7 for installation instructions.
After the EBC is installed, proceed to paragraph 4.5 if installing an Integrated Transformer Cabinet (ITC), to
paragraph 4.6 if installing an Sidecar Integrated Accessory Cabinet-Bypass (SIAC-B), to paragraph 4.7 if
installing a Integrated Accessory Cabinet-Tie (IAC-T), to paragraph 4.8 if installing a Integrated Accessory
Cabinet-Tie and Bypass (IAC-TB), or to paragraph 4.9 if installing an Integrated Accessory Cabinet-Distribution
(IAC-D); otherwise, proceed to paragraph 4.10 to complete the wiring of the UPS.
4.5 Integrated Transformer Cabinet Installation
If installing an Integrated Transformer Cabinet (ITC), refer to the Eaton 93E Integrated Transformer Cabinet
Installation Manual listed in paragraph 1.7 for installation instructions.
After the ITC is installed, proceed to paragraph 4.6 if installing an Sidecar Integrated Accessory Cabinet-Bypass
(SIAC-B), to paragraph 4.7 if installing an IAC-B, or to paragraph 4.9 if installing an IAC-D; otherwise, proceed
to paragraph 4.10 to complete the wiring of the UPS.
4.6 Sidecar Integrated Accessory Cabinet-Bypass
If installing an SIAC-B, refer to the Eaton 93E Sidecar Integrated Accessory Cabinet-Bypass Installation and
Operation Manual listed in paragraph 1.7 for installation instructions.
After the SIAC-B is installed, proceed to paragraph 4.9 if installing Integrated Accessory Cabinet-Distribution;
otherwise, proceed to paragraph 4.10 to complete the wiring of the UPS.
4.7 Integrated Accessory Cabinet-Tie
If installing an IAC-T, refer to the Eaton 93E Integrated Accessory Cabinet-Tie and Bypass Installation and
Operation Manual listed in paragraph 1.7 for installation instructions.
After the IAC-T is installed, proceed to paragraph 4.9 if installing Integrated Accessory Cabinet-Distribution;
otherwise, proceed to paragraph 4.10 to complete the wiring of the UPS.
4.8 Integrated Accessory Cabinet-Tie and Bypass
If installing an IAC-TB, refer to the Eaton 93E Integrated Accessory Cabinet-Tie and Bypass Installation and
Operation Manual listed in paragraph 1.7 for installation instructions.
After the IAC-TB is installed, proceed to paragraph 4.9 if installing Integrated Accessory Cabinet-Distribution;
otherwise, proceed to paragraph 4.10 to complete the wiring of the UPS.
4.9 Integrated Accessory Cabinet-Distribution
If installing Integrated Accessory Cabinet-Distribution (IAC-D), refer to the Eaton 93E Integrated Accessory
Cabinet-Distribution Installation and Operation Manual listed in paragraph 1.7 for installation instructions.
After the IAC-D is installed, proceed to paragraph 4.10 to complete the wiring of the UPS.
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-9
4.10 External Power Wiring Installation
To install wiring:
1. Install conduit for UPS input and output wiring.
2. Route the wiring to the UPS terminal blocks on the back of the UPS. See Figure 4-6 for wiring access
information and Figure 4-7 for terminal locations.
3. Connect phase A, B, C, and Neutral (single-feed only) rectifier input power wiring from the utility source to
the rectifier input and neutral terminals. See paragraph 3.2.2 for wiring and termination requirements.
For a detailed view of the UPS terminal block, see Figure 4-8.
4. If wiring a dual-feed system, proceed to Step 5; otherwise, proceed to Step 6.
5. Connect phase A, B, and C, and Neutral bypass input power wiring from the utility source to the bypass
input terminals and neutral terminals. See paragraph 3.2.2 for wiring and termination requirements.
For a detailed view of the UPS terminal block, see Figure 4-8.
6. Connect phase A, B, and C, and Neutral (if required) power wiring from output terminals and neutral
terminals to the critical load. See paragraph 3.2.2 for wiring and termination requirements.
For a detailed view of the UPS terminal block, see Figure 4-8.
WARNING
As a result of the connected loads high leakage current is possible. Connection to earth ground is
required for safety and proper product operation. Do not check UPS operation by any action that
includes removal of the earth (ground) connection with loads attached.
7. Ground the UPS according to local and/or national electrical wiring codes by routing and connecting the
ground wire to the input ground lug. See Figure 4-7 for UPS terminal locations.
For a detailed view of the UPS ground terminals, see Figure 4-8.
8. If wiring interface connections, proceed to paragraph 4.11; otherwise, proceed to Step 9.
9. Install the power terminal cover top using the provided hardware (see Figure 4-9).
10. Install the power terminal cover right and left sides using the provided hardware.
11. Proceed to paragraph 4.13.
NOTE Without accessory cabinets, conduit and wiring enter from the bottom of the UPS
conduit landing plate. With accessory cabinets, wiring can be installed between the
UPS and accessory cabinets by using conduit or by routing wiring through the
power terminal cover base wiring channels.
NOTE Do not install the Power Terminal Cover Left and/or Right Side covers if wiring
adjacent ancillary cabinets (such as an EBC or IAC) using the power terminal base
wiring channel.
UPS System Installation
4-10 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 4-7. Power Terminal Locations
N
DC Input from External
Battery + and –
(Optional)
(See Figure 4-8 for detail)
AC Input to UPS Rectifier
(A, B, C, N)
(See Figure 4-8 for detail)
AC Output to Critical Load
(A, B, C, N)
(See Figure 4-8 for detail)
AC Input to UPS Bypass
(A, B, C, N)
(Optional)
(See Figure 4-8 for detail)
Ground Terminals
Back
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-11
Figure 4-8. Power Terminal Detail
DC Input from
External Battery +
DC Input from
External Battery -
Neutral (N)
AC Output to
Critical Load
Ground Terminals
AC Input to
UPS Rectifier
AC Input to
UPS Bypass
Phase A (L1)
Phase B (L2)
Phase C (L3)
Neutral (N)
Phase A (L1)
Phase B (L2)
Phase C (L3)
Neutral (N)
Phase A (L1)
Phase B (L2)
Phase C (L3)
UPS System Installation
4-12 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 4-9. Power Terminal Cover Top Installation
Power Terminal Cover
Top Installed
Power Terminal Cover
Left Side Installed
Power Terminal Cover
Right Side Installed
Back
NOTE Do not install the Power Terminal Cover Left and/or Right Side covers if wiring adjacent ancillary cabinets
(such as an EBC or IAC) using the power terminal base wiring channel.
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-13
4.11 Installing Interface Connections
4.11.1 Installing Building Alarm Connections
To install wiring:
1. Verify the UPS system is turned off and all power sources are removed. See Chapter 6, “UPS Operating
Instructions,“ for shutdown instructions.
2. To locate the appropriate terminals and review the wiring and termination requirements, see
paragraph 3.2.3, Table 4-1, Figure 4-10, Figure 4-11, and Figure 4-12.
Figure 4-10. Interface Terminal Locations
Mini-Slot Communication Bays
(See Figure 4-11 for detail)
Interface Terminals
(See Figure 4-11 for detail)
Top Rear Panel
Back
UPS System Installation
4-14 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 4-11. Interface Terminal Detail (Terminal Cover Removed)
Figure 4-12. Building Alarm Terminal Block Connector Assignments
3. Route the wiring to the terminal block:
a. If not already removed, remove the power terminal cover right and left sides (see Figure 4-9). Retain
the cover top and hardware for later use.
b. If not already removed, remove the power terminal cover top. Retain the cover top and hardware for
later use.
Table 4-1. Building Alarm Connections
Building Alarm Terminal Name Description
1 Building Alarm 1 + Input: Programmable UPS alarm, activated by a remote dry contact closure.
2 Building Alarm 1 –
3 Building Alarm 2 + Input: Programmable UPS alarm, activated by a remote dry contact closure.
4 Building Alarm 2 –
5 Building Alarm 3 + Input: Programmable UPS alarm, activated by a remote dry contact closure.
6 Building Alarm 3 –
Mini-Slot
Communication Bay 1
Mini-Slot
Communication Bay 2
REPO Terminals
Parallel CAN Output (RJ45)
Parallel CAN Input (RJ45)
(See Figure 4-19 for Detail)
Building Alarm Terminals
(See Figure 4-12 for Detail)
Pull Chain Terminals
Building Alarm 1
UPS
Building Alarm 2
Building Alarm 3
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-15
c. Remove the screws securing the top rear panel (see Figure 4-10). Supporting the panel, tilt the panel
away from the cabinet and disconnect the fan connectors from the wiring harnesses.
d. Remove the panel. Retain the panel and hardware for later use.
e. Remove the interface terminal cover (see Figure 4-13). Retain the cover and hardware for later use.
f. Punch or drill a hole in the power terminal cover base (see Figure 4-5, Figure 4-6, and Figure 4-14) for
the interface wiring conduit.
g. Route the wiring along the interface wiring channel (see Figure 4-14) until the wire clears the shelf.
h. Route the wire along the shelf under the interface housing to the wiring access (see Figure 4-15).
i. Supporting the top rear panel at the back of the cabinet, reconnect the fan connectors to the wiring
harnesses.
j. Reinstall the top rear panel by tilting into position and securing the panel using the retained hardware.
k. Reinstall the power terminal cover top using the retained hardware.
l. Install the power terminal cover right and left sides using the provided hardware.
4. Connect the building alarm interface wiring as shown in Table 4-1 and Figure 4-12.
5. Reinstall the interface terminal cover using the retained hardware.
6. If wiring generator interface connections, proceed to paragraph 4.11.2; if wiring parallel connections,
proceed to paragraph 4.11.3; if wiring Mini-Slot connections, proceed to paragraph 4.11.4; if wiring REPO
connections, proceed to paragraph 4.12; otherwise, proceed to Step 7.
7. Install the power terminal cover top using the provided hardware (see Figure 4-9).
8. Install the power terminal cover right and left sides using the provided hardware.
9. Close the UPS outside door and secure the latch.
10. Proceed to paragraph 4.13.
NOTE The two upper fans are attached to the top rear panel.
NOTE Conduit and wiring enter from the bottom of the conduit landing plate.
UPS System Installation
4-16 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 4-13. Interface Terminal Cover
Interface Terminal Cover Installed
Interface Terminal Cover
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-17
Figure 4-14. Interface Conduit Landing and Wiring Channel
Figure 4-15. Interface Wiring Access
Wiring Access
Interface Wiring Channel
Shelf
Interface conduit landing area
Power Terminal Cover Base
Wiring Access
UPS System Installation
4-18 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
4.11.2 Generator Interface Connections
If High-Efficiency (HE) mode is enabled and the UPS will be fed by a site generator at any time, an On Generator
building alarm must be wired and configured to a Building Alarm Input. Wiring the On Generator sensing circuit
to a building alarm allows the UPS to optimize its operation with the generator by transferring the UPS from HE
mode to Standard Normal (double conversion) mode.
To Install wiring:
1. Verify the UPS system is turned off and all power sources are removed. See Chapter 6, “UPS Operating
Instructions,“ for shutdown instructions.
2. To locate the appropriate terminals and review the wiring and termination requirements, see
paragraph 3.2.3, Table 4-1, Figure 4-10, Figure 4-11, and Figure 4-12.
3. Route the wiring to the terminal block:
a. If not already removed, remove the power terminal cover right and left sides (see Figure 4-9). Retain
the cover top and hardware for later use.
b. If not already removed, remove the power terminal cover top. Retain the cover top and hardware for
later use.
c. Remove the screws securing the top rear panel (see Figure 4-10). Supporting the panel, tilt the panel
away from the cabinet and disconnect the fan connectors from the wiring harnesses.
d. Remove the panel. Retain the panel and hardware for later use.
e. Remove the interface terminal cover (see Figure 4-13). Retain the cover and hardware for later use.
f. Punch or drill a hole in the power terminal cover base (see Figure 4-5, Figure 4-6, and Figure 4-14) for
the interface wiring conduit.
g. Route the wiring along the interface wiring channel (see Figure 4-14) until the wire clears the shelf.
h. Route the wire along the shelf under the interface housing to the wiring access (see Figure 4-15).
i. Supporting the top rear panel at the back of the cabinet, reconnect the fan connectors to the wiring
harnesses.
j. Reinstall the top rear panel by tilting into position and securing the panel using the retained hardware.
NOTE 1 An UPS building alarm input is used to indicate On Generator.
NOTE 2 Any pair of unused building alarm terminals may be used for On Generator
connections.
NOTE 3 Program the building alarm to read On Generator and for either Normally Open
(default) or Normally Closed as required by the generator sensing output.
NOTE 4 If installing interface wiring connections between standalone cabinets, conduit
must be installed between cabinets.
NOTE 5 Disconnect terminal block plugs from terminal blocks to wire plugs.
NOTE The two upper fans are attached to the top rear panel.
NOTE Conduit and wiring enter from the bottom of the conduit landing plate.
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-19
k. Reinstall the power terminal cover top using the retained hardware.
l. Install the power terminal cover right and left sides using the provided hardware.
4. Connect the building alarm interface wiring as shown in Table 4-1 and Figure 4-12.
5. Reinstall the interface terminal cover using the retained hardware.
6. If wiring parallel connections, proceed to paragraph 4.11.3; if wiring Mini-Slot connections, proceed to
paragraph 4.11.4; if wiring REPO connections, proceed to paragraph 4.12; otherwise, proceed to Step 7.
7. Install the power terminal cover top using the provided hardware (see Figure 4-9).
8. Install the power terminal cover right and left sides using the provided hardware.
9. Close the UPS outside door and secure the latch.
10. Proceed to paragraph 4.13.
4.11.3 Installing Parallel Pull Chain and CAN Control Wiring and Connections
To install wiring:
1. Verify the UPS system is turned off and all power sources are removed. See Chapter 6, “UPS Operating
Instructions,“ for shutdown instructions.
2. To locate the appropriate terminals and review the wiring and termination requirements, see
paragraph 3.2.3, Table 4-2, Figure 4-10, Figure 4-11, and Figure 4-16.
Figure 4-16. Pull Chain Terminal Block Connector Assignments
3. Route the wiring to the terminal block:
a. If not already removed, remove the power terminal cover right and left sides (see Figure 4-9). Retain
the cover top and hardware for later use.
b. If not already removed, remove the power terminal cover top. Retain the cover top and hardware for
later use.
c. Remove the screws securing the top rear panel (see Figure 4-10). Supporting the panel, tilt the panel
away from the cabinet and disconnect the fan connector from the wiring harness.
d. Remove the panel. Retain the panel and hardware for later use.
Table 4-2. Pull Chain Connections
Pull Chain Terminal Name Description
1 Pull Chain + Output: Backup control for parallel operation.
2 Pull Chain –
NOTE The lower fan is attached to the top rear panel.
Pull Chain
UPS
UPS System Installation
4-20 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
e. Remove the interface terminal cover (see Figure 4-13). Retain the cover and hardware for later use.
f. Punch or drill a hole in the power terminal cover base (see Figure 4-5, Figure 4-6, and Figure 4-14) for
the interface wiring conduit.
g. Route the wiring along the interface wiring channel (see Figure 4-14) to the wiring access
(see Figure 4-15). Secure the wiring to the four mounting clips provided using Zip ties.
h. Supporting the top rear panel at the back of the cabinet, reconnect the fan connector to the wiring
harness.
i. Reinstall the top rear panel by tilting into position and securing the panel using the retained hardware.
j. Reinstall the power terminal cover top using the retained hardware.
k. Install the power terminal cover right and left sides using the provided hardware.
4. Route and install RJ-45 Controller Area Network (CAN) cables between the UPS cabinets. See Figure
Figure 4-11 and Figure 4-17 for wiring information.
5. Route and install pull chain wiring between the UPS cabinets and cabinet MOBs. See Figure 4-11,
Figure 4-16, and Figure 4-17 for wiring information.
6. Reinstall the interface terminal cover using the retained hardware.
7. If wiring Mini-Slot connections, proceed to paragraph 4.11.4; if wiring REPO connections, proceed to
paragraph 4.12; otherwise, proceed to Step 8.
8. Install the power terminal cover top using the provided hardware (see Figure 4-9).
9. Install the power terminal cover right and left sides using the provided hardware.
10. Proceed to paragraph 4.13.
4.11.4 Installing Mini-Slot Interface Connections
For installation and setup of an Mini-Slot card, contact an Eaton service representative (see paragraph 1.7)
To install wiring:
1. If not already installed, install the LAN drop.
2. Route and install the LAN and other cables to the appropriate Mini-Slot cards. See Figure 4-10 and
Figure 4-11 for Mini-Slot communication bay locations.
3. Refer to the manual supplied with the Mini-Slot card for operator instructions.
4. If wiring REPO connections, proceed to paragraph 4.12; otherwise, proceed to Step 5.
5. Install the power terminal cover top using the provided hardware (see Figure 4-9).
6. Install the power terminal cover right and left sides using the provided hardware.
7. Proceed to paragraph 4.13.
NOTE Conduit and wiring enter from the bottom of the conduit landing plate.
NOTE LAN drop for use with Mini-Slot cards must be provided by the customer.
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-21
Figure 4-17. Parallel UPS Control Wiring
UPS 1 UPS 2 UPS 3 UPS 4
IN OUT IN OUT IN OUT IN OUT
CAN BUS CAN BUS CAN BUS CAN BUS
CN3 CN6 CN3 CN6 CN3 CN6 CN3 CN6
1212 12 12 12 12 12 12 12
RJ-45 CABLE RJ-45 CABLE RJ-45 CABLE
TERMINATING
JUMPER
TERMINATING
JUMPER
BUILDING
ALARM CN9
BUILDING
ALARM CN9
BUILDING
ALARM CN9
BUILDING
ALARM CN9
PULLCHAIN
CN4
PULLCHAIN
CN4
PULLCHAIN
CN4
PULLCHAIN
CN4
NO NC
COM
NO NC
COM
NO NC
COM
NO NC
COM
NO NC
COM
NO NC
COM
NO NC
COM
NO NC
COM
M
O
B
1
M
O
B
2
M
O
B
3
M
O
B
4
TIE CABINET
CUSTOMER
TERMINAL
BLOCK
CONNECTIONS
32 4259810261514162721202228
16
5
712
11
13 18
17
19 24
23
TWISTED
PAIRS
UPS System Installation
4-22 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
4.12 Installing a REPO Switch
A latching-type Remote Emergency Power-off (REPO) switch can be used in an emergency to shut down the
UPS and remove power to the critical load from a location away from where the UPS is installed. Figure 4-18
shows a REPO switch.
To Install a REPO switch:
1. Verify the UPS system is turned off and all power sources are removed. See Chapter 6, “UPS Operating
Instructions,“ for shutdown instructions.
2. Securely mount the REPO switch. Recommended locations include operator's consoles or near exit
doors. See Figure 3-4 for enclosure dimensions and wiring knockouts.
3. To locate the appropriate terminals and review the wiring and termination requirements, see
paragraph 3.2.3, Table 4-3, Figure 4-10, Figure 4-11, and Figure 4-19.
Figure 4-18. REPO Switch
NOTE 1 Before installing a REPO switch, verify that the UPS was installed according to the
instructions in paragraphs 4.2 through 4.11.
NOTE 2 When installing the REPO switch, you must install conduit between the device and
the UPS cabinet for wiring the switch.
NOTE 3 The REPO switch must be a normally-open or normally-closed latching-type switch
not tied into any other circuits.
NOTE 4 This procedure is intended for installing the Eaton-supplied REPO switch. If
installing another manufacturer's switch, use this procedure, and Figure 4-20 and
Figure 4-21 as a guide.
NOTE 5 The REPO switch wiring must be in accordance with NEC Article 725 Class 2
requirements.
REPO Switch (Front View) Contact Block (Back View, Faceplate Removed)
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-23
Figure 4-19. REPO Terminal Block Connector Assignments
4. Route the REPO wiring to the terminal block:
a. If not already removed, remove the power terminal cover right and left sides (see Figure 4-9). Retain
the cover top and hardware for later use.
b. If not already removed, remove the power terminal cover top. Retain the cover top and hardware for
later use.
c. Remove the screws securing the top rear panel (see Figure 4-10). Supporting the panel, tilt the panel
away from the cabinet and disconnect the fan connectors from the wiring harnesses.
d. Remove the panel. Retain the panel and hardware for later use.
e. Remove the interface terminal cover (see Figure 4-13). Retain the cover and hardware for later use.
f. Punch or drill a hole in the power terminal cover base (see Figure 4-5, Figure 4-6, and Figure 4-14) for
the REPO conduit.
g. Route the wiring along the interface wiring channel (see Figure 4-14) until the wire clears the shelf.
h. Route the wire along the shelf under the interface housing to the wiring access (see Figure 4-15).
i. Supporting the top rear panel at the back of the cabinet, reconnect the fan connectors to the wiring
harnesses.
j. Reinstall the top rear panel by tilting into position and securing the panel using the retained hardware.
k. Reinstall the power terminal cover top using the retained hardware.
l. Install the power terminal cover right and left sides using the provided hardware.
5. Connect the wiring as shown in Table 4-4 and Figure 4-20 for a normally-open REPO or Table 4-5 and
Figure 4-21 for a normally-closed REPO.
Table 4-3. REPO Connections
REPO Terminal Description
1Input: normally-closed dry contact used to activate UPS EPO from a remote switch.
2
3Input: normally-open dry contact used to activate UPS EPO from a remote switch.
4
NOTE The two upper fans are attached to the top rear panel.
NOTE Conduit and wiring enter from the bottom of the conduit landing plate.
Normally Closed
REPO Contacts
Normally Open
REPO Contacts
UPS
UPS System Installation
4-24 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
6. If using a normally-closed REPO switch, connect a jumper wire between pins 3 and 4 on the REPO
terminal block.
7. If you are installing multiple REPO switches, wire additional switches in parallel with the first REPO.
8. If required, install wiring from the REPO switch to the trip circuitry of the upstream protective devices. A
second contact block is provided on the REPO switch for this function (see Figure 4-18). The REPO switch
wiring must be in accordance with NEC Article 725 Class 2 requirements.
9. Reinstall the interface terminal cover using the retained hardware.
Figure 4-20. Normally-Open REPO Switch Wiring
Table 4-4. Normally-Open REPO Wire Terminations
From REPO Station(s)
Switch Contact Block
(Either Block)
To REPO Terminal Block
on Back of UPS Cabinet Wire Size Tightening Torque
3 NO 3 Twisted Wires (2)
1422 AWG
(0.754.0 mm2)
7lbin
(0.8 Nm)
4 NO 4
Table 4-5. Normally-Closed REPO Wire Terminations
From REPO Station(s)
Switch Contact Block
(Either Block)
To REPO Terminal Block
on Back of UPS Cabinet Wire Size Tightening Torque
3 NO 1 Twisted Wires (2)
1422 AWG
(0.754.0 mm2)
7lbin
(0.8 Nm)
4 NO 2
3
1
2
4
3
4
REPO
Switch
(NO)
Twisted
Wires
REPO TB
NOTE REPO switch rating is 24 Vdc, 1A minimum.
NOTE The REPO switch must be a latching-type switch not tied to any other circuits.
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-25
Figure 4-21. Normally-Closed REPO Switch Wiring
4.13 Connecting Internal Battery Strings
DANGER
This battery section contains its own energy source. Risk of electric shock. Do not touch
uninsulated battery terminals. The internal wiring may carry LETHAL VOLTAGES.
WARNING
Internal battery strings should be connected by a qualified electrical contractor knowledgeable of
battery systems, and required precautions.
CAUTION
Connect battery strings only after all wiring is complete.
The UPS is shipped with each battery tray string electrically disconnected. To connect the battery tray strings:
1. If not already open, open the front door (see Figure 4-1) by lifting the latch from the bottom and turning to
the right (counterclockwise) and swing the door open.
2. Remove the screws securing the bottom internal safety shield panel (see Figure 4-22) and remove the
panel to gain access to the battery section (see Figure 4-23). Retain the hardware for later use.
3. Connect the red and black connectors marked with the white flags (see Figure 4-24) for each set of
batteries on the battery shelf.
4. Connect the black connectors (see Figure 4-24) for each set of batteries on the battery shelf.
5. Connect the red connectors (see Figure 4-24) for each set of batteries on the battery shelf.
3
1
2
4
1
2
REPO
Switch
(NC)
Twisted
Wires
REPO TB
NOTE REPO switch rating is 24 Vdc, 1A minimum.
NOTE The REPO switch must be a latching-type switch not tied to any other circuits.
UPS System Installation
4-26 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
6. Repeat Step 3 through Step 5 for each battery shelf (see Figure 4-23) to complete the battery string
connections.
7. Reinstall the internal safety shield panel removed in Step 2.
8. Close the outside door and secure the latch.
Figure 4-22. Battery Location
NOTE The Eaton 93E-40 model has battery strings installed on three shelves. The Eaton
93E–60/40 and Eaton 93E–60/60 models have battery strings installed on four
shelves.
(Batteries are located behind
safety shield.)
Bottom Internal Safety Shield Panel
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-27
Figure 4-23. Battery Section
Battery Section
Battery Trays
Battery Strings
Battery Shelf
NOTE The Eaton 93E-40 model has battery strings installed on three shelves. The Eaton
93E–60/40 and Eaton 93E–60/60 models have battery strings installed on four shelves.
UPS System Installation
4-28 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 4-24. Battery String Connections
4.14 Initial Startup
Startup may be performed by the customer’s battery qualified electrical contractor for single (not parallel) UPS
installations without any accessory cabinets such as an External Battery Cabinet.
Startup and operational checks for parallel systems or installations with accessory cabinets must be performed
by an authorized Eaton Customer Service Engineer, or the warranty terms specified on page W-1 become void.
This service is offered as part of the sales contract for the UPS. Contact an Eaton service representative in
advance (usually a two-week notice is required) to reserve a preferred startup date.
4.15 Completing the Installation Checklist
The final step in installing the UPS system is completing the following Installation Checklist. This checklist
ensures that you have completely installed all hardware, cables, and other equipment. Complete all items listed
on the checklist to ensure a smooth installation. Make a copy of the Installation Checklist before filling it out,
and retain the original.
After the installation is complete, an Eaton Customer Service Engineer must verify the operation of the UPS
system and commission it to support the critical load. The service representative cannot perform any
installation tasks other than verifying software and operating setup parameters. Service personnel may request
a copy of the completed Installation Checklist to verify all applicable equipment installations have been
completed.
Red
Connectors
Black
Connectors
Red Connector
Black Connector White Flags
NOTE The Installation Checklist MUST be completed prior to starting the UPS system for
the first time.
UPS System Installation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 4-29
Installation Checklist
oAll packing materials and restraints have been removed from each cabinet.
oThe UPS cabinet is placed in its installed location
oAll conduits and cables are properly routed to the UPS and any ancillary cabinets.
oAll power cables are properly sized and terminated.
oNeutral conductors are installed.
oA ground conductor is properly installed.
oBuilding alarms are wired appropriately. (Optional)
oLAN drops are installed. (Optional)
oLAN connections have been completed. (Optional)
oThe REPO device is mounted in its installed location and its wiring is terminated inside the
UPS cabinet. (Optional)
oA jumper wire is connected between pins 3 and 4 on the REPO terminal block if using a normally-closed
REPO switch. (Optional)
oInternal battery strings are connected after all other wiring is complete.
oAll terminal cover plates are installed.
oAccessories are mounted in installed locations and wiring is terminated inside the UPS cabinet. (Optional)
oAir conditioning equipment is installed and operating correctly.
oThe area around the installed UPS system is clean and dust-free. (Eaton recommends that the UPS be
installed on a level floor suitable for computer or electronic equipment.)
oAdequate workspace exists around the UPS and other cabinets.
oAdequate lighting is provided around all UPS equipment.
oA 120 Vac service outlet is located within 7.5 meters (25 feet) of the UPS equipment.
oStartup and operational checks are performed by an authorized Eaton Customer Service Engineer for parallel
systems or installations with accessory cabinets.
Parallel System Installation Checklist
oEach cabinet in the parallel system is placed in its installed location.
oAll conduits and cables are properly routed to the UPSs and to the parallel tie cabinet.
oAll power cables are properly sized and terminated.
oNeutral conductors are installed between cabinets as required.
oground conductors are properly installed.
oCAN wiring between the UPSs is properly installed.
oPull chain wiring between the UPSs is properly installed.
oAdequate workspace exists around the UPSs, parallel tie cabinet, and other cabinets.
oStartup and operational checks are performed by an authorized Eaton Customer Service Engineer for parallel
systems.
UPS System Installation
4-30 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Notes
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
Section 2
Operation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 5-1
Chapter 5 Understanding UPS Operation
5.1 UPS System Overview
The Eaton 93E UPS is a continuous-duty, solid-state, transformerless, three-phase, true online system that
provides conditioned and uninterruptible AC power to the UPS system's output and critical load.
The basic system consists of a rectifier, battery converter, inverter, monitoring/operation control panel,
integrated communication server, and digital signal processor (DSP) logic. Figure 5-1 shows the main elements
of the UPS system.
If utility power is interrupted or falls outside the parameters specified in Chapter 9, “Product Specifications,”
the UPS uses a backup battery supply to maintain power to the critical load for a specified period of time or
until the utility power returns. For extended power outages, the UPS allows you to either transfer to an
alternative power system (such as a generator) or shut down your critical load in an orderly manner.
Figure 5-1. Main Elements of the UPS System
The emergency bypass consists of a continuous static switch, and a bypass switchgear. The bypass switchgear
is located in series with the static switch. The static switch is armed and ready during normal operation.
5.2 Single UPS
A single UPS operates independently to support an applied load from the inverter, providing conditioned and
uninterruptible AC power to the critical load from the output of the module. During an outage, the inverter
continues to operate, supporting power to the load from the battery supply. If the unit requires service, applied
loads are transferred to the internal bypass either automatically or manually. With the exception of an optional
external battery cabinet, no other cabinets or equipment are required for the single UPS to successfully support
its applied loads.
AC Input to
Rectifier/
Charger
AC Output
to Critical
Load
Input
Breaker
Rectifier
Switchgear
Battery
Switchgear
Battery
Converter
Battery
Inverter
Switchgear
UPS Cabinet
Bypass
Switchgear
Static
Switch
Digital
Metering
InverterRectifier
Power Module
AC Input to
Bypass
Understanding UPS Operation
5-2 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
5.2.1 Modes
The Eaton 93EUPS supports a critical load in four different modes of operation:
lIn High-Efficiency (HE) Normal mode, commercial AC power is supplied directly to the critical load through
the internal bypass and transfers automatically to Standard Normal mode (double-conversion on demand) if
an abnormal condition is detected. HE mode is the default normal operating mode.
lIn Standard Normal mode, the critical load is supplied by the inverter, which derives its power from rectified
utility AC power. In this mode, the battery charger also provides charging current for the battery, if needed.
lIn Bypass mode, the critical load is directly supported by utility power.
lIn Battery mode, the battery provides DC power, which maintains inverter operation. The battery supports
the critical load.
The following paragraphs describe the differences in the UPS operating modes, using block diagrams to show
the power flow during each mode of operation.
5.2.2 High-Efficiency Normal Mode
When the UPS is operating in HE mode, commercial AC power is supplied directly to the critical load through
the internal bypass with the power module in a standby state. If a commercial power brownout, blackout,
overvoltage, undervoltage, or out-of-tolerance frequency condition occurs the system forward transfers to
normal mode (double-conversion on demand) or battery mode. When the input line returns to normal operating
range, the UPS returns to HE operation. For charging batteries in HE mode, the UPS will revert to normal mode
to charge the batteries, then return to HE mode when charge cycle is complete.
HE mode is the default normal operating mode, and not an alarm condition. While the UPS is in this mode, the
NORMAL light on the front display will illuminate.
5.2.3 Standard Normal Mode
During Standard Normal mode, power for the system is derived from a utility input source through the rectifier
switchgear. Three-phase AC input power is converted to DC using IGBT devices to produce a regulated DC
voltage to the inverter. When the battery switchgear is closed the battery is charged directly from the regulated
rectifier output through a buck or boost DC converter, depending on the system voltage and the size of the
battery string attached to the unit.
Figure 5-2 shows the path of electrical power through the UPS system when the UPS is operating in Normal
mode.
The battery converter derives its input from the regulated DC output of the rectifier and provides either a
boosted or bucked regulated DC voltage charge current to the battery. The battery is always connected to the
UPS and ready to support the inverter should the utility input become unavailable.
The inverter produces a three-phase AC output to a customer's load without the use of a transformer. The
inverter derives regulated DC from the rectifier and uses IGBT devices and pulse-width modulation (PWM) to
produce a regulated and filtered AC output. The AC output of the inverter is delivered to the system output
through the inverter switchgear.
If the utility AC power is interrupted or is out of specification, the UPS automatically switches to Battery mode
to support the critical load without interruption. When utility power returns, the UPS returns to Normal mode.
Understanding UPS Operation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 5-3
Figure 5-2. Path of Current Through the UPS in standard Normal Mode
If the UPS becomes overloaded or unavailable, the UPS switches to Bypass mode. The UPS automatically
returns to Normal mode when the overload condition is cleared and system operation is restored within
specified limits.
If the UPS suffers an internal failure, it switches automatically to Bypass mode and remains in that mode until
the failure is corrected and the UPS is back in service.
Rectifier Inverter
Battery
Converter
Battery
Switchgear
Main Power Flow
Output
Inverter
Switchgear
Bypass Input
Rectifier
Switchgear
Input
Breaker
Rectifier
Input
Switchgear
Breakers
Closed
Open
Battery
Trickle Current
De-Energized
Energized
Static
Switch
Bypass
Switchgear
Understanding UPS Operation
5-4 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
5.2.4 Bypass Mode
CAUTION
The critical load is not protected from voltage or frequency fluctuations or power outages while
the UPS is in Bypass mode.
The UPS automatically switches to Bypass mode if it detects an overload, load fault, or internal failure. The UPS
can also be transferred from Normal mode to Bypass mode manually. The bypass source supplies the
commercial AC power to the load directly. Figure 5-3 shows the path of electrical power through the UPS
system when operating in Bypass mode.
In Bypass mode, the output of the system is provided with three-phase AC power directly from the system
input. While in this mode, the output of the system is not protected from voltage or frequency fluctuations or
power outages from the source. Some power line filtering and spike protection is provided to the load but no
active power conditioning or battery support is available to the output of the system in the Bypass mode of
operation.
The internal bypass is comprised of a solid-state, silicon-controlled rectifier (SCR) continuous static switch, and
the bypass switchgear. The static switch is used instantaneously anytime the inverter is unable to support the
applied load. The continuous static switch is wired in series with the bypass switchgear, and together they are
wired in parallel with the rectifier and inverter.
The static switch, being an electronically-controlled device, can be turned on immediately to pick up the load
from the inverter while inverter switchgear opens to isolate the inverter. The bypass switchgear is normally
closed, ready to support the static switch unless the bypass input source becomes unavailable.
If the UPS transfers to Bypass mode from Normal mode due to any reason other than operator intervention,
the UPS automatically attempts to transfer back to Normal mode (up to three times within a ten minute period).
The fourth transfer locks the critical load to the bypass source and requires operator intervention to transfer.
Figure 5-3. Path of Current Through the UPS in Bypass Mode
Bypass Input Static
Switch
Bypass
Switchgear
Rectifier Inverter
Inverter
Switchgear
Rectifier
Switchgear
Input
BreakerRectifier
Input Output
Battery
Converter
Battery
Switchgear
Main Power Flow
Switchgear
Breakers
Closed
Open
Battery
Trickle Current
De-Energized
Energized
Understanding UPS Operation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 5-5
5.2.5 Battery Mode
The UPS automatically transfers to Battery mode if a utility power outage occurs, or if the utility power does
not conform to specified parameters. In Battery mode, the battery provides emergency DC power that the
inverter converts to AC power.
Figure 5-4 shows the path of electrical power through the UPS system when operating in Battery mode.
Figure 5-4. Path of Current Through the UPS in Battery Mode
During a utility power failure, the rectifier no longer has an AC utility source from which to supply the DC output
voltage required to support the inverter. The rectifier switchgear opens and the battery instantaneously
supplies energy to the battery converter. The converter boosts the voltage so that the inverter can support the
customer's load without interruption. If bypass is common with the rectifier input, the bypass switchgear also
opens. The opening of the rectifier and the bypass switchgear prevent system voltages from bleeding
backwards through the static switch and rectifier snubber components to the utility source.
If the input power fails to return or is not within the acceptance windows required for normal operation, the
battery continues discharging until a DC voltage level is reached where the inverter output can no longer
support the connected loads. When this event occurs, the UPS issues another set of audible and visual alarms
indicating SHUTDOWN IMMINENT. Unless the rectifier has a valid AC input soon, the output can be supported
for only two minutes before the output of the system shuts down. If the bypass source is available, the UPS
transfers to bypass instead of shutting down.
If at any time during the battery discharge the input power becomes available again, the input and the bypass
switchgear close and the rectifier begins to supply DC current to the converter and inverter. At this point, the
unit returns to Normal mode. Depending on the total load and the duration of the battery discharge, battery
current limit alarms may be seen for a short time due to the current required to recharge the battery.
Bypass Input Static
Switch
Bypass
Switchgear
Rectifier Inverter
Inverter
Switchgear
Rectifier
Switchgear
Input
Breaker
Rectifier
Input Output
Battery
Converter
Battery
Switchgear
Main Power Flow
Switchgear
Breakers
Closed
Open
Battery
Trickle Current
De-Energized
Energized
Understanding UPS Operation
5-6 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
5.3 Single UPS Unit System Oneline Configurations
The system oneline drawings in this section show the simplified internal structure of the UPS, battery supply,
and basic maintenance bypass.
Oneline Drawing UPS Model
Voltage
System TypeInput Output
See Figure 5-5 93E-40 208/220 208/220 Single Reverse Transfer UPS with Internal Battery (No
External Battery Capability)
See Figure 5-6 93E–60/40
93E–60/60 208/220 208/220 Single Reverse Transfer UPS with Internal Battery and
External Battery Capable
See Figure 5-7 93E–60/40
93E–60/60 208/220 208/220 Single Reverse Transfer UPS with Internal and External
Batteries
Understanding UPS Operation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 5-7
Figure 5-5. UPS System Oneline – 93E-40 Internal Battery (No External Battery Capability)
AC Input to
Bypass 4 Wire
A-B-C Rotation
(optional)
L1, L2, L3,
N (single-feed only)
Input Breaker
Internal Single-Feed
Jumper
L1, L2, L3, N
AC Input to
UPS Rectifier
4 Wire A-B-C
Rotation
AB
Pull Chain
Remote EPO
Parallel CAN
Mini-Slot
Interface
Interface Board
NOTE Callout letters A, B, and D map to Table 3-5.
UPS CABINET
UPM 2
UPM 1
Internal Battery
Static
Switch
Rectifier
Fuse
Fuse
Inverter
Battery
Converter
Fuses
Rectifier
Fuse
Fuse
Inverter
Battery
Converter
Fuses
L1, L2,
L3, N
AC Output to
Critical Load
D
Bypass
Switchgear
Rectifier
Switchgear
Inverter
Switchgear
Battery
Switchgear
Rectifier
Switchgear
Inverter
Switchgear
Battery
Switchgear
Understanding UPS Operation
5-8 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 5-6. UPS System Oneline – Internal Battery and External Battery Capable
AC Input to
Bypass 4 Wire
A-B-C Rotation
(optional)
Input Breaker
Internal Single-Feed
Jumper
L1, L2, L3, N
AC Input to
UPS Rectifier
4 Wire A-B-C
Rotation
AB
Pull Chain
Remote EPO
Parallel CAN
Mini-Slot
Interface
Interface Board
UPM 2
UPM 1
Internal Battery
Static
Switch
Rectifier
Fuse
Fuse
Inverter
Battery
Converter
Fuses
Rectifier
Fuse
Fuse
Inverter
Battery
Converter
Fuses
L1, L2,
L3, N
AC Output to
Critical Load
D
UPS CABINET
Battery Breaker
External
Battery Input
NOTE Callout letters A, B, C, and D map to Table 3-5.
C
Bypass
Switchgear
Rectifier
Switchgear
Inverter
Switchgear
Battery
Switchgear
Rectifier
Switchgear
Inverter
Switchgear
Battery
Switchgear
L1, L2, L3,
N (single-feed only)
Understanding UPS Operation
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 5-9
Figure 5-7. UPS System Oneline – Internal and External Batteries
Battery
Breaker
EXTERNAL BATTERY
CABINET
(Not supplied with the UPS)
NOTE Callout letters A, B, C, and D map to Table 3-5.
AC Input to
Bypass 4 Wire
A-B-C Rotation
(optional)
Input Breaker
Internal Single-Feed
Jumper
L1, L2, L3, N
AC Input to
UPS Rectifier
4 Wire A-B-C
Rotation
AB
Pull Chain
Remote EPO
Parallel CAN
Mini-Slot
Interface
Interface Board
UPM 2
UPM 1
Internal Battery
Static
Switch
Rectifier
Fuse
Fuse
Inverter
Battery
Converter
Fuses
Rectifier
Fuse
Fuse
Inverter
Battery
Converter
Fuses
L1, L2,
L3, N
AC Output to
Critical Load
D
UPS CABINET
Battery Breaker
CExternal
Battery Input
Bypass
Switchgear
Rectifier
Switchgear
Inverter
Switchgear
Battery
Switchgear
Rectifier
Switchgear
Inverter
Switchgear
Battery
Switchgear
L1, L2, L3,
N (single-feed only)
Understanding UPS Operation
5-10 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
This page intentionally left blank.
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-1
Chapter 6 UPS Operating Instructions
This section describes how to operate the UPS.
6.1 UPS Controls and Indicators
The controls and indicators identified and described in this section are used to control and monitor UPS
operation. Figure 6-1 shows the controls and indicators and Figure 6-2 shows the UPS breakers.
Figure 6-1. UPS Controls and Indicators
NOTE 1 Before starting the UPS, ensure all installation tasks are complete and a preliminary
startup has been performed by authorized service personnel. The preliminary
startup verifies all electrical interconnections to ensure the installation was
successful and the system operates properly.
NOTE 2 Read this section of the manual and have thorough knowledge of UPS operation
before attempting to operate any of the controls.
Control Panel
Door Latch
UPS Operating Instructions
6-2 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 6-2. UPS Breakers
6.1.1 Control Panel
The control panel is used to set up and control the UPS, and to monitor UPS operation. For a description of the
UPS control panel functions, see paragraph 6.2.
6.1.2 Circuit Breakers
lInput Circuit Breaker – The Input circuit breaker is used to control the AC input to the UPS rectifier.
lBattery Circuit Breaker – The optional Battery circuit breaker is used to control the DC input to the UPS
when the External Battery Cabinet (EBC) capable option is installed. This breaker disconnects both internal
and external batteries.
Input Breaker
Battery Breaker (EBC
capable option only.)
UPS Operating Instructions
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-3
6.2 Using the Control Panel
The following paragraphs describe the UPS control panel, including controls and indicators, and how to monitor
UPS operation. The control panel (see Figure 6-3) is located on the front door of the UPS.
Figure 6-3. UPS Control Panel
The control panel consists of:
lA liquid crystal display (LCD) (1)
lMenu navigation pushbutton switches (2)
lA vertical column of status indicators (3). See paragraph 6.2.1.
The following paragraphs describe using the UPS control panel to monitor the UPS. See paragraph 6.3 for use
of the operational controls.
When the unit powers up, the screen displays the Eaton logo as shown in Figure 6-3. To advance to the Main
Menu and Mimic screen, press any control panel pushbutton once.
6.2.1 Status Indicators
The four symbols on the right side of the control panel are status indicators. These colored light emitting diode
(LED) lamps work with the alarm horn to let you know the operating status of the UPS.
Table 6-1 describes the status indicators.
2
1
3
Table 6-1. Status Indicators
Indicator Status Description
On The UPS is in Normal mode. The power module is supplying power to the critical load.
Off The UPS is turned off.
On The UPS is in Battery mode. Because Battery mode is a normal condition of the UPS, the Normal indicator also
remains illuminated.
On The UPS is in Bypass mode. The critical load is supported by the bypass source. The Normal indicator is not
illuminated when the system is in Bypass mode.
On The UPS has an active alarm and requires immediate attention. The LCD shows the highest priority active alarms.
All alarms are accompanied by an audible horn. To silence the horn, press any control panel pushbutton once. The
Alarm indicator may be illuminated along with other indicators.
Flashing There is a new UPS alarm condition. The indicator flashes until acknowledged by pressing any control panel
pushbutton once.
Green
Yellow
Yellow
Red
UPS Operating Instructions
6-4 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
6.2.2 System Events
When the UPS system is running in Normal mode, it continually monitors itself and the incoming utility power.
In Battery or Bypass modes, the UPS may issue alarms to let you know exactly what event caused the change
from Normal mode. System events on the UPS can be indicated by horns, lights, messages, or all three.
Select the EVENTS symbol from the menu bar on the main menu screen to display the active events screen.
This screen shows any currently active alarms, notices, or commands. This screen shows any currently active
alarms, notices, or commands. For more information on using the events screen, see paragraph 6.2.6.
lSystem Event Horns – The system event horn beeps to alert an operator that an event needing attention is
taking place. The horn cycles at a half-second rate.
lSystem Event Indicators – The status indicators on the UPS control panel work with the event horn to let
the operator know when the UPS is operating in any mode other than normal. Only the Normal
mode indicator is illuminated during normal UPS system operation. The other indicators illuminate to
indicate alarms or events. When an alarm occurs, first check these indicators to see what type of event has
taken place. For descriptions of the status indicators, see paragraph 6.2.1.
lSystem Event Messages – When a system event occurs, a message appears on the LCD in the UPS status
area. This message is also written to the Events Log and may be added to the History Log. The messages
are divided into four categories: alarms, notices, status, and commands.
UPS Operating Instructions
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-5
6.2.3 Using the LCD and Pushbuttons
The LCD on the control panel provides an operator interface with the UPS system. Figure 6-4 identifies the
display areas discussed in the following sections.
Figure 6-4. Parts of the LCD
AThe UPS status area automatically scrolls between the Eaton model number, current date and time, active
alarms, UPS status, load percent, and battery runtime for the UPS. The top line of display blinks while
scrolling when the system needs attention. Some notices and alarms may be accompanied by an audible
horn. To silence the horn, press any control panel pushbutton once. Shown is a typical alarm message. For
more information about alarms and notices, see paragraph 6.2.2.
BThe information area contains data about UPS status and operations.
CThe menu bar shows the symbols of the available screens. To select a screen, highlight the screen symbol
using the navigation pushbuttons and then press the RETURN pushbutton.
DThe navigation pushbuttons function depending on the screen displayed. Use the Up, Down, Left, and
Right pushbuttons to scroll through available screens and the Esc and Enter pushbuttons to select menu
screens and functions.
You can use the LCD and the pushbuttons to:
lLook at a log of UPS events (alarms, notices, and commands) (see paragraph 6.2.6)
lMonitor UPS operation (see paragraph 6.2.6)
lSet UPS parameters (see paragraph 6.2.6)
lControl UPS operation (see paragraphs 6.2.6 and 6.2.7)
After approximately 10 minutes, the display screen darkens. To restore the screen, press any pushbutton once.
Alarm:
Alarm:Alarm:
Alarm: Output
OutputOutput
Output AC
ACAC
AC Under
UnderUnder
Under Voltage
VoltageVoltage
Voltage
A
B
C
D
Meter Events History Controls Setup
UPS Operating Instructions
6-6 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
6.2.4 Using the Menu
The UPS menu bar allows you to display data in the information area to help you monitor and control UPS
operation. Table 6-2 shows the basic menu structure.
6.2.5 Mimic Screen
Figure 6-5 shows the Main Menu and Mimic screen. To select the Mimic screen from the Meters, Events,
History, Controls, or Setup screens, press the ESC pushbutton on the current menu bar.
The Mimic screen shows the internal components of the UPS cabinet and a real-time graphical representation
of the operating status of the system.
Figure 6-5. Main Menu and Mimic Screen
Table 6-2. Display Function Menu Map
Menu Option Description
METERS Displays performance meters for the system or critical load.
EVENTS Displays the list of Active System Events.
HISTORY Displays a historical log of system events.
CONTROLS Displays the System Control screen.
SETUP Allows you to set the date and time for the time stamp, set the display language, the unit name, and
meter subscripts, change the password, and view the firmware version numbers.
ESC Returns to Main Menu and Mimic screen from the Meters, Events, History, Controls, or Setup
screens. Returns to the main System Setup Level screen from a setup submenu.
Return arrow acknowledges or executes a command, or saves a setting.
Up and down arrows scroll through screens and lists or highlight settings.
Left and right arrows select or adjust settings displayed on the screen.
ESC
ESC
ESC
Eaton 93E Series UPS
UPS Operating Instructions
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-7
6.2.6 Display Menu Operation
Table 6-3 describes the menu functions and how to use them.
Table 6-3. Display Menu Operation
Function Subfunction Operation
Meters – UPS The Meter screens show the UPS meter readings for the unit. The default voltage displayed on these
screens is phase-to-neutral. These can be changed to display the voltage phase-to-phase
(A-B, B-C, C-A). Use the LEFT or RIGHT arrow pushbuttons to select the METER symbol on the main
menu bar, to display the Meter screens. To scroll through the meter screens, press the UP or DOWN
arrow pushbutton. The current UPS readings are displayed in the information area of the screen.
Output – UPS The Output screen shows output voltage (phasetoneutral), output current (each phase), and frequency
being supplied by the UPS, as well as the kVA, kW, and power factor measurements.
Input – UPS The Input screen shows input voltage (phasetoneutral), input current (each phase), and frequency of
the incoming utility source, as well as the kVA, kW, and power factor measurements.
Bypass The Bypass screen shows the bypass input voltage (phasetoneutral), input current (each phase), and
frequency of the incoming utility source, as well as the kVA, kW, and power factor measurements.
Battery – UPS The Battery screen displays the battery voltage (Vdc) and the battery current (Idc).
Events Use the LEFT or RIGHT arrow pushbuttons to select the EVENTS symbol on the main menu bar to
display the Events screens. A listing of all system events that are currently active is displayed. The
most recent event is listed first. As events clear, they are removed from the Events listing. To scroll
through the events, press the UP or DOWN arrow pushbutton.
History Use the LEFT or RIGHT arrow pushbuttons to select the HISTORY symbol on the main menu bar to
display the History screen. The history Log lists up to 512 events in chronological order, with the most
recent event listed last (once 512 is reached, the earliest event is overwritten). The end of the log (the
most recent events) is displayed first; scroll upward to view older event listings. To scroll through the
events, press the UP or DOWN arrow pushbutton.
Setup – User Function Selection This screen can be used to display user information and show the firmware versions installed. Use the
LEFT or RIGHT arrow pushbuttons to select the SETUP symbol on the main menu bar to display the
Setup screen. Use the UP or DOWN arrow pushbutton to highlight the function desired, then press
the RETURN pushbutton to display the function screen. See Figure 6-6 for a typical screen display.
User Info The User Info screen provides the model, CTO and serial numbers of the UPS, the Output voltage,
frequency, and kVA rating, the input voltage rating, and the battery run time rating. Use the LEFT or
RIGHT arrow pushbuttons to select USER on the Setup menu bar. Use the UP or DOWN arrow
pushbutton. to select Info, then press the RETURN pushbutton to display the function screen. To
return to the System Setup screen, press the ESC pushbutton.
About The About screen provides the firmware version numbers installed on the UPS. Use the LEFT or
RIGHT arrow pushbuttons to select USER on the Setup menu bar. Use the UP or DOWN arrow
pushbutton. to select About. To return to the System Setup screen, press the ESC pushbutton.
Setup – Config
(System Level 1 Setup)
Password To enter a password if required, use the LEFT or RIGHT arrow pushbutton to select the password
character position. Use the UP or DOWN arrow pushbutton to change the password character. Once
the password is entered, select DONE and then press the RETURN pushbutton. The System Setup
Level 1 menu screen is displayed. The default System Setup Level 1 password is 0101.
Function Selection This screen can be used to set the date and time, change the display language, enter a unit name,
change the meter style, perform lamp test, clear the history log, and enter a password to access
Level 1 functions. Use the LEFT or RIGHT arrow pushbuttons to select the SETUP symbol on the main
menu bar to display the Setup screen. Use the LEFT or RIGHT arrow pushbutton to select CONFIG
on the Setup menu bar. Enter a password if required.
Clock The Clock Setup screen allows the selection of either month/day/year or day/month/year formats and
daylight savings time for display on the screen and for logging events in the Event and History Logs.
Use the UP or DOWN arrow pushbutton to select CLOCK to display the Clock screen. Use the UP or
DOWN arrow pushbutton to highlight the desired format, then press the RETURN pushbutton to
display the Set Date and Time screen. To return to the System Setup screen, press the ESC
pushbutton.
UPS Operating Instructions
6-8 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Setup – Config
(System Level 1 Setup)
(continued)
Set Date and Time
MM/DD/YYYY
The Set Date and Time MM/DD/YYYY screen allows the internal date and time of the UPS to be set in
the month/day/year format. The date and time information is used for display on the screen and for
logging events in the Event and History Logs. Use the LEFT or RIGHT arrow pushbutton to highlight
the setting to be changed. Use the UP or DOWN arrow pushbutton to make the change. When
finished making changes, use the LEFT or RIGHT arrow pushbutton to highlight SAVE and the UP or
DOWN arrow pushbutton to select YES. To complete the save function and return to the System
Setup screen, select the RETURN arrow pushbutton.
Set Date and Time
DD/MM/YYYY
The Set Date and Time DD/MM/YYYY screen allows the internal date and time of the UPS to be set in
the day/month/year format. The date and time information is used for display on the screen and for
logging events in the Event and History Logs. Use the LEFT or RIGHT arrow pushbutton to highlight
the setting to be changed. Use the UP or DOWN arrow pushbutton to make the change. When
finished making changes, use the LEFT or RIGHT arrow pushbutton to highlight SAVE and the UP or
DOWN arrow pushbutton to select YES. To complete the save function and return to the System
Setup screen, select the RETURN arrow pushbutton.
Language The Language Setup screen allows the display menu language to be selected. Use the UP or DOWN
arrow pushbutton to highlight Language, then press the RETURN pushbutton to display the Language
screen. Use the UP or DOWN arrow pushbutton to highlight the desired language, then press the
RETURN pushbutton. To return to the System Setup screen, press the ESC pushbutton.
Unit Name The Unit Name Setup screen allows a unit name to be entered. Use the UP or DOWN arrow
pushbutton to highlight Unit Name, then press the RETURN pushbutton to display the Unit Name
screen. Use the LEFT or RIGHT arrow pushbutton to highlight the character to be changed. Use the
UP or DOWN arrow pushbutton to make the change. When finished making changes, use the LEFT or
RIGHT arrow pushbutton to highlight SAVE and the UP or DOWN arrow pushbutton to select YES.
To complete the save function and return to the System Setup screen, select the RETURN arrow
pushbutton. To return to the System Setup screen, press the ESC pushbutton.
Meters The Meters Setup screen allows the Meters Screen display style to be selected. Use the UP or
DOWN arrow pushbutton to highlight Meters, then press the RETURN pushbutton to display the
Meters screen. Use the UP or DOWN arrow pushbutton. to highlight the desired style, then press the
RETURN pushbutton. To return to the System Setup screen, press the ESC pushbutton.
Lamp Test The Lamp Test screen allows the control panel status lamps to be tested. Use the UP or DOWN arrow
pushbutton to highlight Lamp Test, then press the RETURN pushbutton to illuminate the status lamps.
To return to the System Setup screen, press the ESC pushbutton.
Clear Log The Clear Log screen allows the history log to be cleared. Use the UP or DOWN arrow pushbutton to
highlight Clear Log, then press the RETURN pushbutton to clear the log. To return to the System
Setup screen, press the ESC pushbutton.
P/W The P/W screen is used to change the System Setup Level 1 password. Use the UP or DOWN arrow
pushbutton to highlight P/W, then press the RETURN pushbutton to display the P/W screen. Use the
LEFT or RIGHT arrow pushbutton to select the password character position. Use the UP or DOWN
arrow pushbutton to change the password character. Once the password is entered, select CHANGE
and then press the RETURN pushbutton.
Controls See paragraph 6.2.7 for details.
Table 6-3. Display Menu Operation
Function Subfunction Operation
UPS Operating Instructions
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-9
Figure 6-6. Typical Initial Setup Screen
6.2.7 System Controls
Select the CONTROLS symbol on the main menu bar, then press the RETURN pushbutton to display the
Controls screen. Normal operation, transfer to bypass, load off, and charger control commands are controlled
through this screen. In addition, the screen displays the current status of the UPS. Figure 6-7 shows the
System Control screen.
Use the or pushbutton to highlight the command screen desired, then press the RETURN pushbutton to
display the command menu screen.
Use the or pushbutton to highlight the command desired.
Table 6-4 describes the control functions and provides instructions to access and use the command menu
screens.
Table 6-5 lists the typical System Status Screen Messages that are displayed during UPS operation.
For detailed information about using the System Controls, see paragraph 6.3.
Status:
Status:Status:
Status: Load
LoadLoad
Load Off
OffOff
Off
Info
InfoInfo
Info
About
AboutAbout
About
User
UserUser
User Config
ConfigConfig
Config Service
ServiceService
Service
UPS Operating Instructions
6-10 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
Figure 6-7. Typical System Control Screen
Status:
Status:Status:
Status: Load
LoadLoad
Load Off
OffOff
Off
Load
LoadLoad
Load Off
OffOff
Off
Load
LoadLoad
Load Off
OffOff
Off
Normal
NormalNormal
Normal
Bypass
BypassBypass
Bypass
UPS
UPSUPS
UPS Battery
BatteryBattery
Battery UPM
UPMUPM
UPM
Disable
DisableDisable
Disable
Enable
EnableEnable
Enable
HE:
Table 6-4. Command Menu Operation
Function Subfunction Operation
UPS Control
Commands
Use the up or down arrow pushbutton to highlight the command function desired, then
press the RETURN pushbutton to execute the command or proceed to further command
screens.
Normal Mode Starts the UPS in High Efficiency (HE) Normal mode or transfers the UPS to HE Normal
mode from Bypass mode.
Bypass Mode Starts the UPS in Normal mode or transfers the UPS to Normal mode from Bypass mode.
High-Efficiency (HE) Mode Transfers the from HE Normal mode to Standard Normal mode.
Transfers the from Standard Normal mode to HE Normal mode.
Battery Control
Commands
Use the up or down arrow pushbutton to highlight the command function desired, then
press the RETURN pushbutton to execute the command.
Charger Turns the battery charger on.
Resting Turns the battery charger off.
Table 6-5. Typical System Status Messages
Function Message
UPS Load Off; Bypass; Online, HE
Bypass Off; On; Available
Charger Charger Resting; Charger
UPS Operating Instructions
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-11
6.3 Single UPS Operation
6.3.1 Starting the UPS in High-Efficiency Normal Mode (Default Mode)
To start the UPS system:
1. Unfasten the front door by lifting the latch from the bottom and turning to the right (counterclockwise) and
swing the door open (see Figure 6-1).
2. Verify that the input breaker is open.
3. If the UPS is EBC capable, verify that the UPS battery breaker is open.
4. Close the UPS input feeder circuit breaker.
5. If an ITC with an input transformer is installed, close the input and UPS input breakers.
6. If an ITC with an input and output transformer is installed, close the input, UPS input, and UPS output
breakers.
7. If the UPS is dual-feed, close the bypass input feeder circuit breaker.
8. Close the input breaker.
9. If the UPS is EBC capable, close the UPS battery breaker.
10. Close the door and secure the latch.
11. If EBCs are installed, close the EBC battery breakers.
12. Observe the UPS control panel display becoming active, indicating logic power.
13. Verify no alarms are active.
14. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
15. If not already selected, select UPS on the System Control screen.
16. On the UPS System Control screen, select the LOAD OFF NORMAL command, then press the
RETURN pushbutton.
NOTE 1 If an External Battery Cabinet (EBC) is installed, refer to the Eaton 93E External
Battery Cabinet Installation Manual listed in paragraph 1.7 for EBC battery
breaker location.
NOTE 2 If an Integrated Transformer Cabinet (ITC) is installed, refer to the Eaton 93E
Integrated Transformer Cabinet Installation Manual listed in paragraph 1.7 for
ITC transformer breaker locations.
NOTE 3 If an Integrated Accessory Cabinet-Distribution (IAC-D) is installed, refer to the
Eaton 93E Integrated Accessory Cabinet-Distribution Installation and Operation
Manual listed in paragraph 1.7 for operating instructions.
NOTE 4 If a Sidecar Integrated Accessory Cabinet-Bypass (SIAC-B) is installed, refer to the
Eaton 93E Sidecar Integrated Accessory Cabinet-Bypass Installation and Operation
Manual listed in paragraph 1.7 for operating instructions.
NOTE If two EBCs are installed, EBC 1 must be closed to supply DC input to the UPS. EBC
2 may be left open, but battery runtime will be reduced.
UPS Operating Instructions
6-12 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
17. If requested, enter the Level 1 password. Default password is 1111.
The rectifier and inverter turn on. The inverter continues to ramp up to full voltage.
Once the inverter reaches full voltage, the UPS inverter switchgear closes and the static switch turns off.
Power is now supplied to the critical load in HE Normal mode. It takes approximately one minute for the
UPS to achieve HE Normal mode.
The Normal status indicator is illuminated.
18. If an ITC with an input and output transformer is installed, close the output breaker.
6.3.2 Starting the UPS in Bypass Mode
If the inverter output of the UPS is not available and the critical load needs to be energized:
CAUTION
In Bypass mode, the critical load is not protected from commercial power interruptions and
abnormalities.
1. Unfasten the front door by lifting the latch from the bottom and turning to the right (counterclockwise) and
swing the door open (Figure 6-1).
2. Verify that the input breaker is open.
3. If the UPS is EBC capable, verify that the UPS battery breaker is open.
4. Close the UPS input feeder circuit breaker.
5. If an ITC with an input transformer is installed, close the input and UPS input breakers.
6. If an ITC with an input and output transformer is installed, close the input, UPS input, and UPS output
breakers.
7. If the UPS is dual-feed, close the bypass input feeder circuit breaker.
8. Close the input breaker.
9. If the UPS is EBC capable, close the UPS battery breaker.
10. Close the door and secure the latch.
11. If EBCs are installed, close the battery breakers.
12. Observe the UPS control panel display becoming active, indicating logic power.
13. Verify no alarms are active.
14. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
15. If not already selected, select UPS on the System Control screen.
16. On the UPS System Control screen, select the LOAD OFF BYPASS command, then press the
RETURN pushbutton.
The critical load is immediately supplied by the bypass source, in Bypass mode.
The BYPASS status indicator is illuminated.
17. If an ITC with an input and output transformer is installed, close the output breaker.
The critical load is immediately supplied by the bypass source, in Bypass mode.
NOTE If two EBCs are installed, EBC 1 must be closed to supply DC input to the UPS. EBC
2 may be left open, but battery runtime will be reduced.
UPS Operating Instructions
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-13
6.3.3 Transfer from Normal to Bypass Mode
To transfer the critical load to Bypass mode:
CAUTION
In Bypass mode, the critical load is not protected from commercial power interruptions and
abnormalities.
1. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. If not already selected, select UPS on the System Control screen.
3. On the UPS System Control screen, select the NORMAL BYPASS command, then press the RETURN
pushbutton.
The UPS transfers to Bypass mode.
The BYPASS status indicator is illuminated. The power module remains on.
WARNING
Power is present inside the UPS cabinet.
6.3.4 Transfer from Bypass to Normal Mode
To transfer the critical load to Normal mode:
1. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. If not already selected, select UPS on the System Control screen.
3. On the UPS System Control screen, select the BYPASS NORMAL command, then press the RETURN
pushbutton.
The UPS transfers to Normal mode. If the power module is not available, the system remains on bypass
and an alarm sounds.
The NORMAL status indicator is illuminated.
6.3.5 Transfer from HE Normal Mode to Standard Normal Mode
To transfer the load to Standard Normal mode:
1. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. If not already selected, select UPS on the System Control screen.
3. On the UPS System Control screen, select the HE: ENABLE DISABLE command, then press the
RETURN pushbutton.
The UPS transfers to Standard Normal mode.
The NORMAL status indicator is illuminated.
UPS Operating Instructions
6-14 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
6.3.6 Transfer from Standard Normal Mode to HE Normal mode
To transfer the load to HE Normal mode:
1. S e l e c t th e CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. If not already selected, select UPS on the System Control screen.
3. On the UPS System Control screen, select the HE: DISABLE ENABLE command, then press the
RETURN pushbutton.
The UPS transfers to HE Normal mode if no abnormal power conditions are detected. If abnormal power
conditions are detected, the UPS will wait and transfer to HE mode when conditions are cleared.
The NORMAL status indicator is illuminated.
6.3.7 UPS and Critical Load Shutdown
To perform maintenance or service on the critical load, shut down power to the load:
1. Turn off all equipment that is being powered by the UPS.
2. Perform the LOAD OFF procedure in paragraph 6.3.10.
The inverter and bypass switchgear open, and the power module is turned off.
3. Perform the battery charger off procedure in paragraph 6.3.8.
The rectifier and battery switchgear open.
WARNING
Power is present inside the UPS cabinet after the upstream input feeder circuit breakers are
opened because of the installed internal batteries.
4. Open the UPS input circuit breaker.
5. Open the UPS input feeder circuit breakers.
6. If the UPS is dual-feed, open the bypass feeder circuit breakers.
7. If the UPS is EBC capable, open the UPS battery breaker.
8. If EBCs are installed, open all EBC battery breakers.
6.3.8 Charger Control
To turn the battery charger on:
1. S e l e c t th e CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. Select Battery on the System Control screen.
3. On the Battery System Control screen, select the RESTING CHARGING command, then press the
RETURN pushbutton.
To turn the battery charger off:
1. S e l e c t th e CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. Select Battery on the System Control screen.
3. On the Battery System Control screen, select the CHARGING RESTING command, then press the
RETURN pushbutton.
UPS Operating Instructions
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-15
6.3.9 Battery Test
To start the battery test:
1. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. Select Battery on the System Control screen.
3. On the Battery System Control screen, select the RESTING TESTING command, then press the
RETURN pushbutton.
6.3.10 Using the UPS LOAD OFF Command
A UPS Load Off is initiated by the Load Off command on the UPS Control screen. The UPS LOAD OFF controls
the UPS output by powering down the UPS and de-energizing the critical load.
The UPS (including Bypass) remains off until restarted.
To use the LOAD OFF command:
1. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. Select UPS on the System Control screen.
3. On the UPS System Control screen, select the NORMAL LOAD OFF or BYPASS LOAD OFF
command depending on the UPS mode, then press the RETURN pushbutton.
The Verify Action screen is displayed, providing a choice to proceed or abort the shutdown.
CAUTION
All power to the critical load is lost when the LOAD OFF is selected in the following step. You
should use this feature only when you want to de-energize the critical load.
4. Select Yes or no, then press the RETURN pushbutton.
Selecting Yes will immediately shut down the UPS and de-energizing the critical load. Selecting No will
abort the shutdown.
CAUTION
Do not attempt to restart the system after Load Off until the cause of the shutdown has been
identified and cleared.
5. To restart the UPS after pressing the LOAD OFF pushbutton, follow the procedure in paragraph 6.3.1 or
6.3.2.
WARNING
Power is present inside the UPS cabinet after the upstream input feeder circuit breakers are
opened because of the installed internal batteries.
NOTE 1 This UPS has a user initiated battery test intended to determine if the
batteries are able to support the load.
NOTE 2 The battery test is only able to be initiated when the battery is fully
charged. This normally occurs within 72 hours of the start of a charging
cycle. The command will not be shown if the test is not able to be run.
UPS Operating Instructions
6-16 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
6.3.11 Using the Remote Emergency Power-off Switch
A UPS emergency power-off is initiated by the REPO pushbutton switch. In an emergency, you can use this
switch to control the UPS output. The REPO switch de-energizes the critical load and powers down the UPS
immediately, without asking for verification.
The UPS, including Bypass, remains off until restarted.
CAUTION
All power to the critical load is lost when the REPO switch is activated in the following step. You
should use this feature only when you want to de-energize the critical load.
To use the REPO switch:
1. Firmly push the red pushbutton until it locks into place. The switch latches into the activated state
(see Figure 6-8).
The rectifier, inverter, battery, and bypass switchgear open, and the power module is turned off
immediately, without asking for verification.
CAUTION
Do not attempt to restart the system after the REPO until the cause of the shutdown has been
identified and cleared.
2. To deactivate the REPO switch in preparation for restarting the UPS, insert the supplied key and rotate
clockwise until the red pushbutton releases (see Figure 6-8). To remove the key, rotate the key back to the
vertical position.
3. Restart the UPS by following the procedure in paragraph 6.3.1 or 6.3.2.
WARNING
Power is present inside the UPS cabinet after the upstream input feeder circuit breakers are
opened because of the installed internal batteries.
Figure 6-8. REPO Operation
NOTE The following instructions are for the Eaton-supplied REPO switch. If a
customer-supplied REPO switch is used, it may not activate in the same manner;
refer to the operating instructions provided with the switch.
Activated
Pushbutton locked into place
Deactivated
Unlock pushbutton to release
UPS Operating Instructions
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-17
6.4 Multiple UPS Parallel Operation
The paragraphs in this section provide operating instructions for a UPS system containing multiple UPSs.
6.4.1 Starting the Parallel UPS in High-Efficiency Normal Mode (Default Mode)
To start the UPS system:
1. Unfasten the front door by lifting the latch from the bottom and turning to the right (counterclockwise) and
swing the door open (see Figure 6-1).
2. Verify that all input breakers are open.
3. If the UPSs are EBC capable, verify that all UPS battery breakers are open.
4. Close all Module Output Breakers (MOBs).
5. Close all UPS input feeder circuit breakers.
6. If the UPSs are dual-feed, close all bypass input feeder circuit breakers.
7. Close all input breakers.
8. If the UPSs are EBC capable, close all UPS battery breakers.
9. Close the door and secure the latch.
10. If EBCs are installed, close all battery breakers.
11. Observe the UPS control panel displays becoming active, indicating logic power.
12. Verify no alarms are active.
13. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
14. If not already selected, select UPS on the System Control screen.
15. On the UPS System Control screen, select the LOAD OFF NORMAL command, then press the
RETURN pushbutton.
NOTE 1 If an External Battery Cabinet (EBC) is installed, refer to the Eaton 93E External
Battery Cabinet Installation Manual listed in paragraph 1.7 for EBC battery
breaker location.
NOTE 2 If an Integrated Accessory Cabinet-Tie (IAC-T) is installed, refer to the Eaton 93E
Integrated Accessory Cabinet-Tie and Bypass Installation and Operation Manual
listed in paragraph 1.7 for operating instructions.
NOTE 3 I an Integrated Accessory Cabinet-Tie and Bypass is installed, refer to the Eaton 93E
Integrated Accessory Cabinet-Tie and Bypass Installation and Operation Manual
listed in paragraph 1.7 for operating instructions.
NOTE 4 If an Integrated Accessory Cabinet-Distribution (IAC-D) is installed, refer to the
Eaton 93E Integrated Accessory Cabinet-Distribution Installation and Operation
Manual listed in paragraph 1.7 for operating instructions.
NOTE 5 Start and control system wide functions from UPS 1.
NOTE For each UPS, if two EBCs are installed, EBC 1 must be closed to supply DC input
to the UPS. EBC 2 may be left open, but battery runtime will be reduced.
UPS Operating Instructions
6-18 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
16. If requested, enter the Level 1 password. Default password is 1111.
All rectifiers and inverters turn on. The inverters continue to ramp up to full voltage.
Once all inverters reaches full voltage, the UPS inverter switchgear closes and the static switches turns
off. Power is now supplied to the critical load in HE Normal mode. It takes approximately one minute for
the UPS to achieve HE Normal mode.
The Normal status indicator is illuminated.
6.4.2 Starting the Parallel UPS in Bypass Mode
If the inverter output of the parallel UPS system is not available and the critical load needs to be energized:
CAUTION
In Bypass mode, the critical load is not protected from commercial power interruptions and
abnormalities.
1. Unfasten the front door by lifting the latch from the bottom and turning to the right (counterclockwise) and
swing the door open (Figure 6-1).
2. Verify that all input breakers are open.
3. If the UPSs are EBC capable, verify that all UPS battery breakers are open.
4. Close all Module Output Breakers (MOBs)
5. Close all UPS input feeder circuit breakers.
6. If the UPSs are dual-feed, close all bypass input feeder circuit breakers.
7. Close all input breakers.
8. If the UPSs are EBC capable, close all UPS battery breakers.
9. Close the door and secure the latch.
10. If EBCs are installed, close all battery breakers.
11. Observe the UPS control panel displays becoming active, indicating logic power.
12. Verify no alarms are active.
13. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
14. If not already selected, select UPS on the System Control screen.
15. On the UPS System Control screen, select the LOAD OFF BYPASS command, then press the
RETURN pushbutton.
The critical load is immediately supplied by the bypass source, in Bypass mode from all UPSs.
The BYPASS status indicator is illuminated.
NOTE For each UPS, if two EBCs are installed, EBC 1 must be closed to supply DC input
to the UPS. EBC 2 may be left open, but battery runtime will be reduced.
UPS Operating Instructions
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-19
6.4.3 Transfer from Normal to Bypass Mode
To transfer the critical load to Bypass mode:
CAUTION
In Bypass mode, the critical load is not protected from commercial power interruptions and
abnormalities.
1. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. If not already selected, select UPS on the System Control screen.
3. On the UPS System Control screen, select the NORMAL BYPASS command, then press the RETURN
pushbutton.
All of the UPSs transfer to Bypass mode.
The BYPASS status indicator is illuminated. The power module remains on.
WARNING
Power is present inside the UPS cabinet.
6.4.4 Transfer from Bypass to Normal Mode
To transfer the critical load to Normal mode:
1. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. If not already selected, select UPS on the System Control screen.
3. On the UPS System Control screen, select the BYPASS NORMAL command, then press the RETURN
pushbutton.
All of the UPSs transfer to Normal mode. If the power module is not available, the system remains on
bypass and an alarm sounds.
The NORMAL status indicator is illuminated.
6.4.5 Transfer from HE Normal Mode to Standard Normal Mode
To transfer the load to Standard Normal mode:
1. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. If not already selected, select UPS on the System Control screen.
3. On the UPS System Control screen, select the HE: ENABLE DISABLE command, then press the
RETURN pushbutton.
All of the UPSs transfer to Standard Normal mode.
The NORMAL status indicator is illuminated.
UPS Operating Instructions
6-20 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
6.4.6 Transfer from Standard Normal Mode to HE Normal mode
To transfer the load to HE Normal mode:
1. S e l e c t th e CONTROLS symbol on the main menu bar. The System Control screen is displayed.
2. If not already selected, select UPS on the System Control screen.
3. On the UPS System Control screen, select the HE: DISABLE ENABLE command, then press the
RETURN pushbutton.
All of the UPSs transfer to HE Normal mode if no abnormal power conditions are detected. If abnormal
power conditions are detected, the UPSs will wait and transfer to HE mode when conditions are cleared.
The NORMAL status indicator is illuminated.
6.4.7 Single UPS Shutdown
To shut down a single UPS:
1. Open the MOB for the UPS being shut down.
2. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
3. If not already selected, select UPS on the System Control screen.
4. On the UPS System Control screen, select the NORMAL UPS OFF command, then press the
RETURN pushbutton.
The inverter and bypass switchgear open, and the power module is turned off on the UPS being shut
down.
Logic power remains on.
WARNING
Power is present inside the UPS cabinet until the upstream input feeder circuit breaker is opened.
5. Open the UPS input feeder circuit breaker for the UPS being shut down.
6. If the UPS is dual-feed, open the bypass feeder circuit breaker for the UPS being shut down.
7. If the UPS is EBC capable, open the UPS battery breaker.
8. If EBCs are installed, open all battery breakers
The UPS is now completely shut down.
6.4.8 Single UPS Restart
To restart a single UPS from a shutdown state:
1. Close the MOB for the UPS being restarted.
2. Close the UPS input feeder circuit breaker for the UPS being restarted.
3. If the UPS is dual-feed, close the bypass feeder circuit breaker for the UPS being restarted.
4. Close the input breaker.
5. If the UPS is EBC capable, close the UPS battery breaker.
6. If EBCs are installed, close the battery breakers.
7. On the UPS being restarted, observe the UPS control panel display becoming active, indicating logic
power.
UPS Operating Instructions
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-21
8. Verify no alarms are active on the UPS being restarted.
9. On the UPS being restarted, select the CONTROLS symbol on the main menu bar. The System Control
screen is displayed.
10. If not already selected, select UPS on the System Control screen.
11. On the UPS System Control screen, select the UPS OFF NORMAL command, then press the
RETURN pushbutton.
12. If requested, enter the Level 1 password. Default password is 1111.
The rectifier and inverter turn on. The inverter continues to ramp up to full voltage.
Once the inverter reaches full voltage, the UPS inverter switchgear closes and the static switch turns off.
Power is now supplied to the critical load in HE Normal mode along with the other UPSs online. It takes
approximately one minute for the UPS to achieve HE Normal mode.
The Normal status indicator is illuminated.
6.4.9 UPS and Critical Load Shutdown
To perform maintenance or service on the critical load, shut down power to the load:
1. Turn off all equipment that is being powered by the UPS parallel system.
2. Transfer the UPSs to bypass by performing the procedure in paragraph 6.4.3.
3. Perform the LOAD OFF procedure in paragraph 6.4.12.
The inverter and bypass switchgear open, and the power module is turned off.
4. Perform the battery charger off procedure in paragraph 6.4.10 for each UPS.
The rectifier and battery switchgear open.
WARNING
Power is present inside the UPS cabinets after the upstream input feeder circuit breakers are
opened because of the installed internal batteries.
5. Open all of the UPS input circuit breakers.
6. Open all of the MOBs.
7. Open all UPSs input feeder circuit breakers.
8. If the UPSs are dual-feed, open all bypass feeder circuit breakers.
9. If the UPSs are EBC capable, open all UPSs battery breakers.
10. If EBCs are installed, open all battery breakers.
UPS Operating Instructions
6-22 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
6.4.10 Charger Control
To turn an individual UPS battery charger on:
1. S e l e c t th e CONTROLS symbol on the main menu bar on the UPS requiring the charger to be turned on.
The System Control screen is displayed.
2. Select Battery on the System Control screen.
3. On the Battery System Control screen, select the RESTING CHARGING command, then press the
RETURN pushbutton.
To turn an individual UPS battery charger off:
1. S e l e c t th e CONTROLS symbol on the main menu bar on the UPS requiring the charger to be turned off.
The System Control screen is displayed.
2. Select Battery on the System Control screen.
3. On the Battery System Control screen, select the CHARGING RESTING command, then press the
RETURN pushbutton.
6.4.11 Battery Test
To start an individual UPS battery test:
1. S e l e c t th e CONTROLS symbol on the main menu bar on the UPS to be tested. The System Control
screen is displayed.
2. Select Battery on the System Control screen.
3. On the Battery System Control screen, select the RESTING TESTING command, then press the
RETURN pushbutton.
6.4.12 Using the UPS LOAD OFF Command
A UPS Load Off is initiated by the Load Off command on the UPS Control screen. The UPS LOAD OFF controls
the UPSs output by powering down the UPS and de-energizing the critical load.
The UPSs (including Bypass) remains off until restarted.
To use the LOAD OFF command:
1. S e l e c t th e CONTROLS symbol on the main menu bar on the UPS to be shut down. The System Control
screen is displayed.
2. Select UPS on the System Control screen.
3. On the UPS System Control screen, select the NORMAL LOAD OFF or BYPASS LOAD OFF
command depending on the UPS mode, then press the RETURN pushbutton.
The Verify Action screen is displayed, providing a choice to proceed or abort the shutdown.
NOTE 1 This UPS has a user initiated battery test intended to determine if the
batteries are able to support the load.
NOTE 2 The battery test is only able to be initiated when the battery is fully
charged. This normally occurs within 72 hours of the start of a charging
cycle. The command will not be shown if the test is not able to be run.
UPS Operating Instructions
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 6-23
CAUTION
All power to the critical load is lost when the LOAD OFF is selected in the following step. You
should use this feature only when you want to de-energize the critical load.
4. Select Yes or no, then press the RETURN pushbutton.
Selecting Yes will immediately shut down the UPS and de-energize the critical load. Selecting No will abort
the shutdown.
5. If another UPS is to be shut down, proceed to that UPS and repeat Step 1 through Step 4.
CAUTION
Do not attempt to restart the system after Load Off until the cause of the shutdown has been
identified and cleared.
6. To restart the UPS after pressing the LOAD OFF pushbutton, follow the procedure in paragraph 6.4.1 or
6.4.2.
WARNING
Power is present inside the UPS cabinet after the upstream input feeder circuit breakers are
opened because of the installed internal batteries.
6.4.13 Using the Remote Emergency Power-off Switch
A UPS emergency power-off is initiated by the REPO pushbutton switch. In an emergency, you can use this
switch to control the UPS output. The REPO switch de-energizes the critical load and powers down the UPSs
immediately, without asking for verification.
The UPSs, including Bypass, remains off until restarted.
CAUTION
All power to the critical load is lost when the REPO switch is activated in the following step. You
should use this feature only when you want to de-energize the critical load.
To use the REPO switch:
1. Firmly push the red pushbutton until it locks into place. The switch latches into the activated state
(see Figure 6-8).
The rectifier, inverter, battery, and bypass switchgear open, and the power module is turned off
immediately, without asking for verification.
CAUTION
Do not attempt to restart the system after the REPO until the cause of the shutdown has been
identified and cleared.
NOTE The following instructions are for the Eaton-supplied REPO switch. If a
customer-supplied REPO switch is used, it may not activate in the same manner;
refer to the operating instructions provided with the switch.
UPS Operating Instructions
6-24 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
2. To deactivate the REPO switch in preparation for restarting the UPS, insert the supplied key and rotate
clockwise until the red pushbutton releases (see Figure 6-8). To remove the key, rotate the key back to the
vertical position.
3. Restart the UPS by following the procedure in paragraph 6.4.1 or 6.4.2.
WARNING
Power is present inside the UPS cabinet after the upstream input feeder circuit breakers are
opened because of the installed internal batteries.
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 7-1
Chapter 7 Communication
This chapter describes the communication features of the Eaton 93E UPS. For terminal wiring information, see
paragraph 3.2.3 and paragraph 4.11. For location of the customer interface panel and terminals, see Figure 4-10
and Figure 4-11.
7.1 Mini-Slot Cards
The Eaton 93E UPS has two standard, factory-installed Mini-Slot communication bays. See Figure 4-10 for bay
locations. The UPS is compatible with the following Mini-Slot cards (see Figure 7-1):
lNetwork Management Card and Modbus/Jbus – provides remote monitoring through a Web browser
interface, e-mail, and a network management system (NMS) using SNMP and connects to a twisted-pair
Ethernet (10/100BaseT) network. The card also provides direct integration of UPS information (meters and
status) to a Building Management System (BMS) using the Modbus RTU protocol.
lNetwork Management Card – provides remote monitoring through a Web browser interface, e-mail, and a
network management system (NMS) using SNMP and connects to a twisted-pair Ethernet (10/100BaseT)
network.
lRelay Card – MS – two types of interfaces via a DB9 connector are available with this card. Dry contact
mode provides a simple way to transmit UPS information to an alarm system, PLC, or computer system via
dry relay contacts. Normal, Bypass, Battery, and Alarm modes can be monitored. See Table 7-1 for default
triggers. RS232 mode provides an RS232 interface for connection to a PC or to a UPS Control display unit.
Jumpers are used to select the interface (contacts or RS232).
lIndustrial Relay Card IRC – MS – indicates the operating status of the UPS system using the customer's
monitoring equipment. The IRC uses isolated normally-open or normally-closed dry relay contacts to indicate
the UPS status. Online, Bypass, Battery, and Alarm modes can be monitored.
LAN and telephone drops for use with Mini-Slot connectivity cards must be supplied by facility planners or the
customer.
For installation, setup, and operation of a Mini-Slot card, refer to the instructions supplied with the Mini-Slot
card. For additional assistance, contact an Eaton service representative (see paragraph 1.7).
Figure 7-1. Optional Mini-Slot Cards
NOTE Only one Network Management Card or Network Management Card and Modbus/
Jbus can be used at one time.
Relay Card – MS Network Management Card
Network Management
Card and Modbus/Jbus
Industrial Relay Card IRC – MS
Communication
7-2 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
7.2 Building Alarm Monitoring
This standard feature lets you connect the UPS to your building alarms, such as smoke detectors or
overtemperature alarms. The customer interface terminals for external connections are located inside the UPS.
Use twisted-pair wires for each alarm input and common.
The building alarms can be programmed to display the alarm functional name.
7.3 Predict Pulse Remote Monitoring and Management Service
The Eaton 93E UPS supports Eaton's PredictPulse remote monitoring and management service. PredictPulse
is a subscription monitoring and management service that collects and analyzes data from connected power
infrastructure devices, providing us with the insight needed to make recommendations and take action on your
behalf. It’s also powered by CA Technologies, bringing together the best in hardware and software.
PredictPulse Service is included at no charge during the first year of Eaton 93E UPS operation (warranty period)
along with the required connectivity parts. Beyond that, it may be purchased with Eaton Support Agreements
or as a standalone subscription after the initial warranty expires. PredictPulse may also be subscribed to for free
as part of a 90-day trial period. PredictPulse availability and first year bundled offers may vary by market. For
more information, visit www.eaton.com/predictpulse.
Table 7-1. Relay Card – MS and Industrial Relay Card IRC – MS Default Triggers
UPS Alarm Relay Trigger Indicator
On Normal K1 UPS supporting the load Normal indicator is illuminated
On Battery K2 UPS on Battery Battery indicator is illuminated
Alarm K3 Summary alarm / Active Alarms Alarm indicator is illuminated
On Bypass K4 UPS on bypass Bypass indicator is illuminated
Battery Low K5 UPS battery voltage level below the low voltage threshold Low Battery warning is active
NOTE Each relay connection has a NO and NC contact and an isolated relay
Table 7-2. Relay Card - MS Contacts
UPS Alarm MS Contacts Active State
On Normal Pin 8 to Pin 5 Closed = UPS is on Normal
Open = UPS on Battery, Bypass, or Offline
On Battery
Pin 4 to Pin 5 Closed = UPS on Normal, Bypass, or Offline
Open = UPS on Battery
Pin 9 to Pin 5 Closed = UPS on Battery
Open = UPS on Normal, Bypass, or Offline
Alarm Pin 2 to Pin 5 Closed = UPS has an active Alarm
Open = UPS has no active Alarms
On Bypass Pin 6 to Pin 5 Closed = UPS is on Bypass
Open = UPS is on Normal, Battery, or Offline
Battery Low Pin 7 to Pin 5
Closed = UPS battery voltage level below the low voltage
threshold
Open = UPS battery voltage level above the low voltage
threshold
NOTE Pin 5 is common for call contacts
Communication
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 7-3
7.3.1 PredictPulse Service Features
PredictPulse provides proactive monitoring, an online dashboard, mobile app with alarm status information and
a monthly report detailing the ongoing health of your Eaton 93E UPS. Features include:
lProactive monitoring that automatically analyzes the status of the Eaton 93E UPS 96 times every day (every
15 minutes). All health data gathered from the unit, current and historical, is analyzed at the Customer
Reliability Center (CRC). Algorithms and sophisticated analytics software is constantly scanning your UPS's
data for potential failures. Anomalies are escalated to a Software and Monitoring analyst or Technical
Support specialist. Critical events are remotely diagnosed to expedite repairs, including smart dispatch of
field technicians with probable cause and likely parts (avoiding return visits due to lack of required parts).
Through this service, the CRC can take pre-emptive, corrective action to ensure the highest level of
availability of your Eaton 93E UPS.
lEasy self-installation in minutes from a wizard installer or directly from the PXGMS card. PredictPulse uses
standard Eaton connectivity hardware, requiring no special software (devices only need to be connected to
a network).
lAbility to give an unlimited number of coworkers access to the real-time data and reports found in
PredictPulse’s online dashboard and mobile app. This allows you to collaborate and Eaton to notify the most
appropriate person responsible for a specific site or device.
lReal-time access to key performance information, alarms and trended health data about your Eaton 93E UPS
via the PredictPulse online dashboard. Depending on the model, the dashboard aggregates all subscribed
devices and provides detailed information about voltages, loads, energy savings, service levels, external
factors such as temperature and humidity, attached batteries, and system availability. All of these factors
contribute to the Relative Performance Index (RPI) score that allows you to compare your unit's health
relative to Eaton's optimum UPS operating levels.
lReal-time alarm events for all subscribed devices via the PredictPulse mobile app (Apple and Android). You
can track all alarms by device. As critical alarms occur, Eaton will acknowledge them so you know when
Eaton has diagnosed the alarm (and pending notification of resolution).
lA monthly summary report that delivers key performance information, alarms and trended health data about
your Eaton 93E UPS, based on the prior month’s data.
lA foundation based on CA Technologies’ leading Data Center Infrastructure Management (DCIM) software
application. This enables powerful reporting, analytics, security, and compatibility with hundreds of power
infrastructure devices.
7.3.2 Installing PredictPulse
A quick start guide and self-installation wizard tool are available at www.eaton.com/predictpulse. The latest
updates, installation tips and information on connecting PredictPulse are also available at that link. For
installation support or questions about PredictPulse, contact predictpulsesupport@eaton.com.
PredictPulse relies on a PXGMS card installed with the UPS to send one-way outbound SMTP e-mails to Eaton,
as well as an Environmental Monitoring Probe (EMP) for battery temperature/humidity monitoring. PredictPulse
is secure as Eaton never communicates through your firewall—it only listens for health data and alarm data—
and uses industry-standard security protocols. By using a common e-mail transport mechanism, you do not
have to open your network to proprietary or potentially unsecure protocols and transports. The PXGMS
Connectivity Card gathers information directly from the UPS and any external sensors that are attached, and
transmits that data every 15 minutes (or 96 times per day), enabling real-time monitoring and advanced virtual
preventive maintenance.
Communication
7-4 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
This page intentionally left blank.
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 8-1
Chapter 8 UPS Maintenance
The components inside the UPS cabinet are secured to a sturdy metal frame. All repairable parts and
assemblies are located for easy removal, with very little disassembly. This design allows authorized service
personnel to perform routine maintenance and servicing quickly.
You must schedule periodic performance checks of your UPS system to keep it running properly. Regular
routine checks of operation and system parameters enable your system to function efficiently for many
trouble-free years.
8.1 Important Safety Instructions
Remember that your UPS system is designed to supply power EVEN WHEN DISCONNECTED FROM THE
UTILITY POWER. The UPS module interiors are unsafe until the DC power source is disconnected and the
electrolytic capacitors are discharged. After disconnecting the utility power and the DC power, authorized
service personnel should wait at least five minutes for capacitor bleedoff before attempting internal access to
the UPS module.
WARNING
lServicing and maintenance should be performed by qualified service personnel only.
lLETHAL VOLTAGE PRESENT. This unit should not be operated with the cabinet doors open or
protective panels removed. Do not make any assumptions about the electrical state of any
cabinet in the UPS system.
Each battery string is an energy source in itself. DO NOT ATTEMPT TO ACCESS ANY INTERNAL AREA OF
THE BATTERY STRING YOURSELF. VOLTAGES ARE ALWAYS PRESENT IN THE BATTERY STRING. If
you suspect that a battery string needs service, contact an Eaton service representative.
If the string requires service contact an Eaton service representative.
Observe these precautions when working on or around batteries:
lRemove watches, rings, or other metal objects.
lUse tools with insulated handles.
lWear rubber gloves and boots.
lDo not lay tools or metal parts on top of batteries.
lDisconnect the charging source prior to connecting or disconnecting terminals.
lDetermine if the battery is inadvertently grounded. If it is, remove the source of the ground. Contact with
any part of a grounded battery can result in electrical shock. The likelihood of such shock is reduced if such
grounds are removed during installation and maintenance.
lWhen replacing batteries, use the same number of sealed, lead-acid batteries.
lProper disposal of batteries is required. Refer to your local codes for disposal requirements.
lDo not dispose of batteries in a fire. Batteries may explode when exposed to flame.
lDo not open or mutilate batteries. Released electrolyte is harmful to the skin and eyes. It may be toxic.
UPS Maintenance
8-2 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
8.2 Performing Preventive Maintenance
The UPS system requires very little preventive maintenance. However, the system should be inspected
periodically to verify that the units are operating normally and that the batteries are in good condition.
8.2.1 DAILY Maintenance
Perform the following steps daily:
1. Check the area surrounding the UPS system. Ensure the area is not cluttered, allowing free access to the
unit.
2. Ensure the air intakes (vents on the front door of the UPS cabinet and the exhaust openings (on the rear of
the UPS cabinet) are not blocked.
3. Ensure the operating environment is within the parameters specified in paragraph 3.2.1 and Chapter 9,
“Product Specifications.”
4. Ensure the UPS is in Normal mode (Normal status indicator is illuminated). If an alarm lamp is illuminated
or the Normal status indicator is not illuminated, contact an Eaton service representative.
8.2.2 MONTHLY Maintenance
Perform the following steps monthly:
1. Monitor system parameters as described in paragraph 6.2, “Using the Control Panel”.
2. Check the UPS air filters (located behind the front door) and wash or replace as necessary. See Figure 8-1
for filter location. Contact an Eaton service representative for replacement filters. To remove the filters:
CAUTION
Verify washed filter is thoroughly dry before reinstalling.
a. Unfasten the front door by lifting the latch from the bottom and turning to the right (counterclockwise)
and swing the door open (see Figure 6-1).
b. Loosen thumbscrews securing filter retaining brackets.
c. Remove the upper and lower foam filters from the frame on the front door.
d. Secure filter retaining brackets with thumbscrews.
e. Replace the washed or new foam filters into the frame on the front door.
f. Close the front door and secure the latch.
3. Record maintenance results and any corrective actions in a suitable log.
UPS Maintenance
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 8-3
Figure 8-1. Air Filter Location
PERIODIC Maintenance
Periodic inspections of the UPS should be made to determine if components, wiring, and connections exhibit
evidence of overheating. Particular attention should be given to the compression lug connections. Maintenance
procedures should specify that the compression lug connections be retorqued to values listed in this manual.
8.2.3 ANNUAL Maintenance
Annual preventive maintenance should be performed only by authorized service personnel familiar with
maintenance and servicing of the UPS system. Contact an Eaton service representative for more information
about service offerings.
8.2.4 BATTERY Maintenance
Contact an Eaton service representative for battery maintenance. Battery replacement and maintenance should
be performed only by authorized service personnel.
8.3 Installing Batteries
Install batteries in accordance with the battery and battery system manufacturer's instructions.
Air Filters
UPS Maintenance
8-4 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
8.4 Recycling the Used Battery or UPS
Contact your local recycling or hazardous waste center for information on proper disposal of the used battery
or UPS.
WARNING
lDo not dispose of the battery or batteries in a fire. Batteries may explode. Proper disposal of
batteries is required. Refer to your local codes for disposal requirements.
lDo not open or mutilate the battery or batteries. Released electrolyte is harmful to the skin and
eyes. It may be toxic.
lA battery can cause electrical shock, burn from high short-circuit current, or fire. Observe proper
precautions.
ATTENTION!
lUne batterie peut prêsenter un risque de choc êlectrique, de brulure, ou d'incendie. Suivre les
précautions qui s'imposent.
lPour le remplacement, utiliser le même nombre et modéle des batteries.
lL'élimination des batteries est règlementée. Consulter les codes locaux à cet effet.
CAUTION
Do not discard the UPS or the UPS batteries in the trash. This product contains sealed, lead-acid
batteries and must be disposed of properly. For more information, contact your local recycling/
reuse or hazardous waste center.
CAUTION
Do not discard waste electrical or electronic equipment (WEEE) in the trash. For proper disposal,
contact your local recycling/reuse or hazardous waste center.
8.5 Maintenance Training
A basic training course, available from Eaton, gives you a competent working knowledge of the UPS system
operation and teaches you how to perform first level corrective maintenance. For more information about
training and other services, contact the Help Desk (see paragraph 1.7).
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 9-1
Chapter 9 Product Specifications
9.1 Model Numbers
The UPS is housed in a free-standing cabinet with safety shields behind the door. The UPS is available in
50 or 60 Hz with various output power ratings.
9.2 Specifications
The following sections detail the input, output, environmental, and battery specifications for the UPS.
9.2.1 UPS Input
Models Power Rating Frequency
Eaton 93E-40 40 kVA 50/60 Hz
Eaton 93E–60/40 40 kVA 50/60 Hz
Eaton 93E–60/60 60 kVA 50/60 Hz
Operating Input Voltage 208/220 Vac
Operating Input Frequency Range 50/60 Hz
Operating Input Current See Table 3-5.
Reduced for Generator
Adjustable
Input Current Harmonic Content 5% THD at full load
Power Factor Minimum 0.99
Line Surges 6 kV OC, 3 kA SC per ANSI 62.41 and IEC 8014
Battery Voltage 216 Vdc
Battery Charging Capacity
Up to a maximum of 40A at any load up to 100% load (supports internal and
internal plus external battery configurations)
Product Specifications
9-2 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
9.2.2 UPS Output
9.2.3 UPS Environmental
9.2.4 UPS Internal Battery Runtimes (in Minutes) at Full load
UPS Output Capacity 100% rated current
Output Voltage Regulation ± 1% (10% to 100% load)
Nominal Output Voltage 208 Vac and 220 Vac nominal
Output Voltage Harmonic Content 2% maximum THD (linear load)
5% maximum THD (nonlinear load)
Output Current See Table 3-5.
Output Voltage Balance < 2% for 100% maximum load imbalance (linear load)
Output Voltage Phase
Displacement
< 2.5 for 100% maximum load imbalance (linear load)
Frequency Regulation 0.1 Hz free running
Synchronous to Bypass ± 4 Hz (default setting)
Frequency Slew Rate 3 Hz per second (default setting)
Load Compatibility 0.8 pF Leading
0.8 pF Lagging
Overload Capability <110% for 10 minutes
<125% for 30 seconds
<150% for 150 milliseconds
>150% for 40 milliseconds
Operating Temperature 0 to 30C (32 to 86F) without derating. The recommended operating
temperature is 25C(77F).
Operating Altitude Maximum 1500m (5000 ft) at 30C without derating
Storage Temperature 25 to +55C, excluding batteries (prolonged storage above 40C causes
rapid battery self-discharge)
Relative Humidity (operating and
storage)
5% to 95% maximum noncondensing
Acoustical Noise Less than or equal to 65 dBA at a 1m distance, per ISO 7779
EMI Emissions and Immunity Meets IEC 62040-2 C3 and FCC Part 15 Subpart B, ICES-003, CISPR 22,
CISPR 24, and VCCI: Class A
Electrostatic Discharge (ESD)
Immunity
Meets IEC 61000-4-5 Level 4 specifications. Withstands up to 4 kV pulse
without damage and with no disturbance or adverse effect to the critical
load.
UPS Model UPS Rating
Number of UPS
Battery Strings Runtime
93E-40 40 kVA 6 7.0
93E–60/40 40 kVA 8 12.0
93E–60/60 60 kVA 8 6.6
NOTE Battery times are approximate and vary depending on the load configuration and battery charge.
Product Specifications
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 9-3
9.2.5 UPS Internal Battery Plus External Battery Cabinet Runtimes (in Minutes) at Full load
UPS Model UPS Rating
Number of UPS
Battery Strings EBC Model Number of EBCs
Number of EBC
Battery Strings Runtime
93E–60/40 40 kVA 8 93E 60EBC 1 4 46.0
93E–60/40 40 kVA 8 93E 60EBC 1 6 65.0
93E–60/40 40 kVA 8 93E 60EBC 2 8 85.2
93E–60/40 40 kVA 8 93E 60EBC 2 12 128.0
93E–60/60 60 kVA 8 93E 60EBC 1 4 27.8
93E–60/60 60 kVA 8 93E 60EBC 1 6 39.3
93E–60/60 60 kVA 8 93E 60EBC 2 8 51.5
93E–60/60 60 kVA 8 93E 60EBC 2 12 77.6
NOTE Battery times are approximate and vary depending on the load configuration and battery charge.
Product Specifications
9-4 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
This page intentionally left blank.
Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3 W-1
Warranty
LIMITED FACTORY WARRANTY FOR THREE-PHASE EATON® 93E UPS AND 93E UPS ACCESSORY PRODUCTS
WARRANTOR: The warrantor for the limited warranties set forth herein is Eaton, an Ohio Corporation
(”Eaton”).
LIMITED WARRANTY: This limited warranty (this ”Warranty”) applies only to the original end-user (the
”End-User”) of the Eaton Three-Phase 93E UPS and 93E UPS Accessory Products (the ”Product”) and cannot
be transferred. This restriction applies even in the event that the Product is initially sold by Eaton for resale to
an EndUser. This Warranty gives you specific legal rights, and you may also have other rights which vary from
State to State (or jurisdiction to jurisdiction).
WHAT THIS LIMITED WARRANTY COVERS: The warrantor warrants, with the terms of this Warranty, that
the Eaton three-phase UPS electronics, Eaton-built accessories, and Eaton -built battery cabinets (individually
and collectively, the ”Warranted Items”) are free from defects in material and workmanship.
For Product installed (and currently located) in the fifty (50) United States and the District of Columbia, if, in the
opinion of Eaton, a Warranted Item is defective, Eaton's sole obligation, at the option of Eaton, will be to
refurbish or replace such defective Warranted Item (including the costs of providing diagnosis, service, and
labor [“labor coverage”]). The defective Warranted Item will be refurbished or replaced onsite at the End-User's
location or such other location as determined by Eaton. Any parts that are replaced may be new or
reconditioned. All parts replaced by Eaton shall become the property of Eaton.
For Product installed (and currently located) outside the fifty (50) United States and the District of Columbia, if,
in the opinion of Eaton, a Warranted Item is defective, Eaton's sole obligation, at the option of Eaton, will be to
refurbish or replace such defective Warranted Item (not including the costs of labor coverage). The defective
Warranted Item will be refurbished or replaced onsite at the End-User's location or such other location as
determined by Eaton. Any parts that are replaced may be new or reconditioned. All parts replaced by Eaton
shall become the property of Eaton.
LIMITED WARRANTY PERIOD: The period covered by this Warranty for Product installed (and currently
located) in the fifty (50) United States and the District of Columbia is six (6) months from the date of Product
purchase for labor coverage when no startup is performed by an authorized Eaton Customer Service Engineer
or Agent or twelve (12) months from the date of Product purchase with startup performed by an authorized
Eaton Customer Service Engineer or Agent and twelve (12) months from the date of Product purchase or
eighteen (18) months from date of Product shipment, whichever occurs first, for the refurbishment/
replacement of parts.
The period covered by this Warranty for Product installed (and currently located) outside the fifty (50) United
States and the District of Columbia is twelve (12) months from the date of Product purchase or eighteen (18)
months from the date of Product shipment, whichever occurs first, for the refurbishment/replacement of parts.
WHAT THIS LIMITED WARRANTY DOES NOT COVER: This Warranty does not cover any defects or
damages caused by: (a) failure to properly store the Product before installation, including the ”trickle charge”
of batteries no later than the date indicated on the packaging; (b) shipping and delivery of the Product if shipping
is FOB Factory; (c) neglect, accident, fire, flood, lightning, vandalism, acts of God, Customer's neglect, abuse,
misuse, misapplication, incorrect installation; (d) repair or alteration not authorized in writing by Eaton personnel
or performed by an authorized Eaton Customer Service Engineer or Agent; or (e) improper testing, operation,
maintenance, adjustment, or any modification of any kind not authorized in writing by Eaton personnel or
performed by an authorized Eaton Customer Service Engineer or Agent.
This Warranty is not valid: if the Product's serial numbers have been removed or are illegible. Any Warranted
Items repaired or replaced pursuant to this Warranty will be warranted for the remaining portion of the original
Warranty subject to all the terms thereof. Eaton does not provide a labor warranty for Product located outside
of the fifty (50) United States or the District of Columbia. Any equipment, parts, or materials included in the
Product and not manufactured by Eaton are warranted solely by the manufacturer of such equipment,
parts, or materials and are not included as part of this Warranty. Batteries are not warranted by Eaton.
Warranty
W-2 Eaton 93E UPS (40–60 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000302—Rev 3
THIS WARRANTY IS THE ENDUSER'S SOLE REMEDY AND IS EXPRESSLY IN LIEU OF, AND THERE ARE
NO OTHER, EXPRESSED OR IMPLIED GUARANTEES OR WARRANTIES (INCLUDING ANY IMPLIED
WARRANTY OF MERCHANTABILITY OR FITNESS FOR ANY PURPOSE, WHICH ARE EXPRESSLY
DISCLAIMED). SOME STATES OR JURISDICTIONS DO NOT ALLOW THE EXCLUSION OF EXPRESS OR
IMPLIED WARRANTIES, SO THE ABOVE EXCLUSION MAY NOT APPLY TO YOU. IN THAT EVENT, SUCH
WARRANTIES ARE LIMITED IN DURATION TO THE LIMITED WARRANTY PERIOD. SOME STATES OR
JURISDICTIONS DO NOT ALLOW LIMITATIONS ON HOW LONG AN IMPLIED WARRANTY LASTS OR
THE EXCLUSION OR LIMITATION OF INCIDENTAL OR CONSEQUENTIAL DAMAGES, SO THE ABOVE
LIMITATIONS AND/OR EXCLUSIONS MAY NOT APPLY TO YOU.
LIMITATION OF LIABILITY: In no event shall Eaton be liable for any indirect, incidental, special or
consequential damages of any kind or type whatsoever, resulting from or in connection with any claim or cause
of action, whether brought in contract or in tort (including negligence and strict liability). Some States or
jurisdictions do not allow the exclusion of limitation of incidental or consequential damages, so the above
limitation or exclusion may not apply to you. Eaton shall not be responsible for failure to provide service or parts
due to causes beyond Eaton's reasonable control. In no case will Eaton's liability under this Warranty exceed
the replacement value of the Warranted Items.
END-USER'S OBLIGATIONS: In order to receive the benefits of this Warranty, the End-User must register the
product warranty (via mail or online at www.powerquality.eaton.com/ProductRegistration “product
registration”); use the Product in a normal way; follow the Product's user's guide; and protect against further
damage to the Product if there is a covered defect.
OTHER LIMITATIONS: Eaton's obligations under this Warranty are expressly conditioned upon receipt
by Eaton of all payments due to it (including interest charges, if any). During such time as Eaton has not
received payment of any amount due to it for the Product, in accordance with the contract terms under
which the Product is sold, Eaton shall have no obligation under this Warranty. Also during such time,
the period of this Warranty shall continue to run and the expiration of this Warranty shall not be
extended upon payment of any overdue or unpaid amounts.
COSTS NOT RELATED TO WARRANTY: The End-User shall be invoiced for, and shall pay for, all services not
expressly provided for by the terms of this Warranty, including without limitation site calls involving an
inspection that determines no corrective maintenance is required. Any costs for replacement equipment,
installation, materials, freight charges, travel expenses, or labor of Eaton representatives outside the terms of
this Warranty will be borne by the End-User.
OBTAINING WARRANTY SERVICE: In the USA, call the Eaton Customer Reliability Center 7x24 at
800-843-9433. Outside of the USA, call your local Eaton sales or service representative, or call the Eaton
Customer Reliability Center in the United States at 919845-3633. For comments or questions about this
Limited Factory Warranty, write to the Customer Quality Representative, 8609 Six Forks Road, Raleigh,
North Carolina 27615 USA.
*P-164000302 3*
P-164000302 3